Section 1KK
This was a project for earthwork / site preparation to expand section 1KK to provide and additional 279 additional burial sites there were 5' x 10' each on a 2 acre plot.
- Remove existing scrub, SOD and topsoil and Haul off anything not re-used
- Haul in clean clay fill material
- Grade and Compact
- Maintain a max 15:1 slope (6.5% grade)
- Stream protection and install silt fence
- Haul in and place 4" of topsoil
- Install SOD over all disturbed areas and maintain until turnover