Section 1KK

This was a project for earthwork / site preparation to expand section 1KK to provide and additional 279 additional burial sites there were 5' x 10' each on a 2 acre plot.


  • Remove existing scrub, SOD and topsoil and Haul off anything not re-used
  • Haul in clean clay fill material
  • Grade and Compact
  • Maintain a max 15:1 slope (6.5% grade)
  • Stream protection and install silt fence
  • Haul in and place 4" of topsoil
  • Install SOD over all disturbed areas and maintain until turnover