Tiling work continued over the last week. The kitchen floor needs grouting and then it will be finished. The walls and floors of the locker rooms are complete with the exception of the around the shower stalls. The front lobby and elevator shaft wall on the first floor are next to be tiled. Interior doors are still be hung and hardware is being installed. Above ceiling inspections are on-going. Once approvals are received the ceiling panels will be installed.
The mason are busy installing the block walls. The thermal lining panels work has started. About half of the first floor ceiling has been installed. Ceilings and columns in rooms designated for burns will have the panels installed. The only concrete work left to complete is the interior stairs.
The roof of the training tower was poured last weeks. The masons have completed all of the exterior walls. They still have some work on interior walls. The scaffolding has been removed from all but one side of the tower. The concrete stairs will need to be formed and poured over the next couple of weeks.
Grading of the site in preparation of paving continues. The site is being cleaned up to make additional room. With the scaffolding being removed from the training tower that area can now be graded. Paving stones for the patio arrived at the end of the week and that work will start this week.