Update June 16, 2018

Classroom/Administration Building

Finishing work continues on the classroom/administration building. Labeling of the above ceiling utilities need to be completed to pass the final above ceiling inspection. Once that has been completed, then the ceiling pads can be put in place. The floors will be started once the pads are in place. The appliances are being installed in the kitchen. Tiles were installed around the elevator door on the first floor. The second floor opening is sheet-rock.

Burn Building

Scaffolding has been removed from around the burn building except for the west end. The mason are working on the third floor. Most of the exterior walls are done. The thermal lining panels have been installed on the first floor ceiling. The panel are also being installed on the columns. The will start the second floor thermal lining next. They have started on the stairs. That work will continue over the next couple of weeks.

Training Tower

I mentioned last week that the scaffolding was removed from all but one side of the training tower. That has allowed the contractor to start the grading process for the training grounds. The first set of stairs was poured last week. It will take a couple of weeks before they are all complete.

Site Work

Sire work around the classroom/administration building continued this past week. The southwest corner of the building was graded and is ready for sod. The patio on the southeast corner was installed. The two (2) flag poles in the patio area were also installed. Light poles in the parking area and driveway are starting to be installed. An extension was installed on the dry hydrant.