Exterior Rendering
Exterior Rendering
Aerial Rendering View
After the community approved the general obligation bond in November 2024, there has been plenty of work going on behind the scenes to make this project a reality. District leadership and school staff have been attending several meetings throughout the design process with the Architect and Engineer (ISG) and the Construction Manager (Hausmann).
Due to the timeline and complexity of the project, it was determined to use the Construction Manager at Risk (CMaR) delivery method for the new Le Mars Elementary School. The selection process began in January 2025 and was completed in April 2025, with the District selecting Hausmann as the Construction Manager (CM). This process allows the Construction Manager to be involved in the design of the project early on, offering consistent budget checks and construction insights to the Owner and Design Team.
Work done to date:
November 2024 - Bond Approval
April 7, 2025 - Construction Manager Award
Project moved to new 26 acre property at Central Avenue and 18th Street
December 19, 2025 - Design Development plans completed
March 4, 2026 - Construction Documents completed
Construction of the new elementary school to serve PreK through 5th grade students is officially underway. This project is a part of a community-wide effort to invest in growth, opportunity, and quality of place. Community leaders, board members, staff, and students gathered to celebrate this exciting milestone for the District.
Site work is underway on the site of the new Le Mars Community Elementary School. The proposed stormwater retention pond has taken shape and site utilities (Storm, Sanitary and Water) are beginning to be installed. Foundation work and surface improvements will begin in the coming weeks.
Aerial view of the Elementary site.
The retaining wall seperating the lower level from the education wings is complete, allowing the construction team to begin foundations for the education wings on the back of the building. Foundations for the front of the building are in progress. Site utilities are generally completed with underground utilities in the building footprint underway. Site preparations for proposed parking lots and drive lanes are complete.