BioEPIC Construction
CURRENT STATUS: March 2025
Electrical and IT rooms build-out ongoing.
B91U MUP commissioning ongoing.
Building 92 commissioning ongoing.
Building energization (EVAP/MEVAP) ongoing.
Greenhouse installation is ongoing.
Furniture installation ongoing.
Bayview Generator commissioning and punchlist in progress.
Building punchlist and walk in progress.
Building final cleanup in progress.
PROJECT CONTACTS
PIMD Project Director/Manager: Gwynne Bankert
PIMD Deputy Project Manager: Connie Lin
PIMD Construction Manager: Rey Espino
EXPECTED IMPACTS
Traffic
During certain phases of the project construction truck traffic and lane closures on Alvarez Road will impact vehicle traffic and shuttle schedules.
Large or wide trucks or equipment will necessitate the closure of Blackberry Gate for several hours. Notifications will be sent directing traffic to use Strawberry Gate during closures.
There will be increased construction equipment and personnel along Alvarez Road from October 2021 through early 2025.
Details, including mitigation efforts, once confirmed will be posted to this page and shared via email and Elements.
Parking
The Bayview parking lot will remain closed throughout construction.
The Blackberry Lot D (The Pit) has been identified for contractor parking overflow (vehicles unable to fit within project laydown). Use caution around construction vehicles and equipment in this area.
Noise, Vibrations, and Dust
The construction activities will be disruptive.
Expected noise will range from heavy construction equipment use to pile drilling related activities to steel erection.
Although dust control measures will be employed by the contractor, there will be some level of dust generated by the project.
SCHEDULE
The schedule is subject to change without notice.
Building EVAP: May - March 2025
Hardscape/Landscape: May - March 2025
Beneficial Occupancy: February 2025
Substantial Completion: March 2025
Final Completion: March 2025