BioEPIC Construction
CURRENT STATUS: July 2024
Electrical and IT rooms build-out in progress.
Overhead mechanical, plumbing, electrical installation ongoing on all levels.
Painting, flooring, and ceiling work in progress.
B91U MUP mechanical commissioning ongoing.
Building 92 mechanical commissioning ongoing.
Site work, underground, and generator installation ongoing.
Building energization in progress.
PROJECT CONTACTS
PIMD Project Director/Manager: Gwynne Bankert
PIMD Deputy Project Manager: Connie Lin
PIMD Construction Manager: Rey Espino
EXPECTED IMPACTS
Traffic
During certain phases of the project construction truck traffic and lane closures on Alvarez Road will impact vehicle traffic and shuttle schedules.
Large or wide trucks or equipment will necessitate the closure of Blackberry Gate for several hours. Notifications will be sent directing traffic to use Strawberry Gate during closures.
There will be increased construction equipment and personnel along Alvarez Road from October 2021 through 2024.
Details, including mitigation efforts, once confirmed will be posted to this page and shared via email and Elements.
Parking
The Bayview parking lot will remain closed throughout construction.
The Blackberry Lot D (The Pit) has been identified for contractor parking overflow (vehicles unable to fit within project laydown). Use caution around construction vehicles and equipment in this area.
Noise, Vibrations, and Dust
The construction activities will be disruptive.
Expected noise will range from heavy construction equipment use to pile drilling related activities to steel erection.
Although dust control measures will be employed by the contractor, there will be some level of dust generated by the project.
SCHEDULE
The schedule is subject to change without notice.
Finishes: July 2023 - July 2024
Building EVAP: May - September 2024
Hardscape/Landscape: May - September 2024
Substantial Completion: October 2024
Final Completion: January 2025