Sitewide Mechanical Project

CURRENT STATUS: April 2024 

PROJECT CONTACTS

EXPECTED IMPACTS

Traffic

Noise and vibration

Utility outage

There is a planned utility outage affecting Buildings 2 and 23 beginning on Thursday, July 11, from 7 a.m. to 7 p.m.

Occupants are not allowed in buildings during electrical outages

SCHEDULE

The schedule is subject to change without notice.

December 2024 (during ALS shutdown): Large equipment installation

February 2024: Projected completion date



OVERVIEW

The new building 2 (B2) cooling plant is a mechanical system upgrade designed to improve the reliability of B2 cooling and science operations. The project will build three new cooling towers to provide cooling water to the chilled water plant and process cooling water loop. Building this additional plant will also relieve demand on the B37 cooling plant, which supports several buildings, including the ALS. 

 PAST VIBRATION TEST ON NOVEMBER 7

What the project team needs from building tenants: