Physical product

Hour 1

Measuring out 2X4's

Hour 2

Cutting 2X4's

Hour 3

Pile of cut 2X4's

Hour 4

making the foundation and the first wall

Hours 5 and 6

Making the lay out of the floor plan

Hours 7-10

The walls sat together for a dry fit

One of the walls being held together while the glue is drying

Hours 11-13

Adding the last exterior wall

Putting in interior walls in

Waiting to see if the glue will hold up the wall for drying

Hour 14

Cutting the siding

Finished Product

SCN_0002.pdf
Physical Project Evaluation