Project Timeline
This timeline provides events for all phases of the Ivy Tech Community College Columbus new campus building project. The timeline is in reverse chronological order to provide the upcoming and most recent events first.
2022
2022 Fall | Project complete
2022 Summer | Move into new building; Poling Hall demolition
2022 Spring | New building complete
2021
2021 Fall | Interior work begins
2021 Summer | Structural steel installed
2021-05-18 | First steel beam set
2021-4-01 | Virtual Groundbreaking Ceremony held to mark beginning of construction
2019
2019-12-20 | Pepper Construction selected as the project Construction Managers
2019-12-20 | Pepper Construction selected as the project Construction Managers
2019-12-13 | IwomotoScott selected as the project Design Architect
2019-12-10 | Construction Manager interviews
2019-12-06 | Design Architects Presentations from 1 to 6 p.m. at the Fair Oaks Mall