This #Project743 website will be the home of construction updates for our staff and community. We invite you to return often as we share our exciting progress.

Construction Update Highlights

Ongoing or Completed Highlights

July 2023

  • Area C - Masonry - 100%
  • Area B Classrooms – Ceiling Grid Complete
  • Area B Classrooms – Painting is Complete
  • Area B Classrooms – Ready for Flooring Installation
  • Area C & D – Duct Installation Continues
  • Mason Block Work Continues - All Areas
  • Area A Soil Correction Commenced
  • Area B Media Center - Framing Continues
  • Area B Saw Cutting – 100%
  • Area C Saw Cutting – Exterior Walls Commenced
  • Area C Flooring Demolition – 100%
  • Hard Demolition Commenced – All Areas
  • Structural Steel Installation Commenced

June 2023

  • Hard Demolition Commenced – All Areas
  • Structural Steel Installation Commenced
  • Shoring for Wall Removal Finishing Soon – All Areas
  • Floor Grinding and Prep Continues – All Areas
  • Main Electrical Utility Relocation – 100%
  • Area B Ceiling Demolition – 100%
  • Area B Flooring Demolition – 100%
  • Area D Ceiling Demolition – 100%
  • Area D Flooring Demolition – 100%
  • Duct Demolition – 100%
  • Site Mobilization for Civil Work – 100%
  • Job Site Office Setup – 100%
  • Preliminary Site Removal (Area A)  – 100%
  • Electrical Utility Relocation – 100%
  • Area C Ceiling Demolition – 100%
  • Area C Flooring Demolition – 100%

Construction Photo Gallery

Anticipated Construction Timeline:

2023 Phase 1 – Elementary School Work
(Areas A, B, C, D, E - Roof, F - Roof)

2024 Phase 2 – High School and Middle School Work
(Areas G, H, I, J, K, L, E - Courtyard Infill)

[  Project Sequencing Plan  ]

In The News

June 5, 2023 - Exciting Progress with Sauk Centre Public Schools Building Project – Time to Break Ground!
June 5, 2023 - Exciting Progress with Sauk Centre Public Schools Building Project – Time to Break Ground!