Construction Update Highlights
Ongoing or Completed Highlights
July 2023
- Area C - Masonry - 100%
- Area B Classrooms – Ceiling Grid Complete
- Area B Classrooms – Painting is Complete
- Area B Classrooms – Ready for Flooring Installation
- Area C & D – Duct Installation Continues
- Mason Block Work Continues - All Areas
- Area A Soil Correction Commenced
- Area B Media Center - Framing Continues
- Area B Saw Cutting – 100%
- Area C Saw Cutting – Exterior Walls Commenced
- Area C Flooring Demolition – 100%
- Hard Demolition Commenced – All Areas
- Structural Steel Installation Commenced
June 2023
- Hard Demolition Commenced – All Areas
- Structural Steel Installation Commenced
- Shoring for Wall Removal Finishing Soon – All Areas
- Floor Grinding and Prep Continues – All Areas
- Main Electrical Utility Relocation – 100%
- Area B Ceiling Demolition – 100%
- Area B Flooring Demolition – 100%
- Area D Ceiling Demolition – 100%
- Area D Flooring Demolition – 100%
- Duct Demolition – 100%
- Site Mobilization for Civil Work – 100%
- Job Site Office Setup – 100%
- Preliminary Site Removal (Area A) – 100%
- Electrical Utility Relocation – 100%
- Area C Ceiling Demolition – 100%
- Area C Flooring Demolition – 100%
Construction Photo Gallery
Anticipated Construction Timeline:
2023 Phase 1 – Elementary School Work
(Areas A, B, C, D, E - Roof, F - Roof)
Construction Commencement – Early Summer 2023
Construction Substantial Completion – Fall 2023
2024 Phase 2 – High School and Middle School Work
(Areas G, H, I, J, K, L, E - Courtyard Infill)
Construction Commencement – Spring 2024
Construction Substantial Completion – Fall 2024
[ Project Sequencing Plan ]