Construction Updates
January 2020 Construction Updates:
Glen Ridge Schools Construction Update
The four ongoing construction projects are getting close to completion. The District appreciates the patience and flexibility of the entire school community that was exhibited throughout the project. This winter, the elementary schools have experienced more consistent heating conditions in their buildings that they traditionally have had during past winters. The inclusion of central air in the elementary schools will create a better learning environment for our students this spring.
Bi-weekly construction meetings with the contractors, our construction manager, our architect, and the administration continue to take place. At this time, safety protocols are reinforced, details about completed work and ongoing work are reviewed, and solutions to unforeseen obstacles are discussed.
Please contact your child’s building principal if there are questions or concerns about any item relating to the construction.
Central School
Recently Completed:
- Permanent blinds were installed this week throughout the building.
- Ladder installed for roof access
- The permanent fence around the chiller was finished last week. The fence enclosed a large area to ensure the proper airflow needed for the chiller to run effectively.
To-Do List:
- The High Street exterior doors are expected to be delivered next week and will be hung shortly afterward
- Classroom signage needs to be hung by each door
- The library doors need the hardware installed
- Punchlist; there are a large number of minor items that need to be addressed before the project is complete
- Over the April break, the parking lot will be sealed and striped with direction arrows, drop off zone, and parking spot lines
- The Historic Preservation Committee approved a school sign that is similar to the Forest Avenue School and Linden Avenue signs. It will be a double-sided sign and placed on the island between the Bloomfield Avenue entrance and exit.
- The elevator inspector wanted additional work completed in the electric room. We are working with the town inspector to get clarification on the required work.
Estimated Date of Completion: End of February 2020
Forest Avenue School
Recently Completed:
- Chiller and switchgear installed
- Trench completed and asphalted
To-Do:
- Exterior water pipe connection from the chiller to the boiler room (scheduled to be completed this week)
- PSE&G install a new transformer on the utility pole (scheduled - tbd)
- Electrical connection from the transformer to the chiller and the switchgear to the boiler room (scheduled to be completed by the end of next week)
- Chilled water pipes testing (scheduled during February break)
- Punch list items will be addressed starting this week with work being completed during after school hours
Estimated Date of Completion: End of February 2020
Linden Avenue School
Recently Completed:
- Chiller and switchgear installed
- Trench completed and asphalted
To-Do:
- Exterior water pipe connection from the chiller to the boiler room (scheduled to be completed this week)
- Electrical connection from the transformer to the chiller and the switchgear to the boiler room (scheduled to be completed by the end of next week)
- PSE&G connection to the new transformer (scheduled - tbd)
- Chilled water pipes testing (scheduled during February break)
- A permanent fence around the chiller and switchgear (scheduled - tbd)
- Punch list items will be addressed starting this week with work being completed during after school hours
Estimated Date of Completion: End of February 2020
Ridgewood Avenue School
Recently Completed:
- Gyms heat transferred from manual to automated system
To-Do:
- Temporary heating installed in the auditorium (scheduled for next week)
- Continue to connect chilled water pipes to classrooms (ongoing)
- Completion of the chilled water component in the boiler room (continuous for the next two weeks)
- Install gas line to chiller (scheduled for the next two weeks)
- Permanent chimney install (scheduled for the February break)
- Punch list items (scheduled - tbd)
Estimated Date of Completion: End of March 2020