Central School Bathroom Corner Sinks
Central School Bathroom Sinks
Central School Classroom
Central School Classroom
Piping insulation continued
Mechanical Piping continued on site
Underground trench work to chiller completed
Fan coil unit installation
Fan coil unit installation commenced
Plumbing fixture installation continued
Self leveling commenced in classrooms
Furniture Delivery
VCT Flooring commenced
VCT Flooring commenced
Glue on top of self leveling
Ceiling tile and lighting installation continued
Lay in lighting installation commenced.
Prime painting commenced in first floor classroom.
Corridor Ceiling grid installed. Corridor prime painted.
First Floor Walls Spackled Taped and Sanded.
Rooftop units set, EPDM roof work completed.
Site work continued in parking lot.
Chiller set on pads and piping connections to boiler room set.
Exterior Pipe Trench Complete.
Bathroom Tile Work Commenced
Bathroom Tile Work Commenced
Ground Floor Corridor Sheetrock lamination commenced
Roof work commenced on site
Roof work commenced on site
Mechanical Room piping commenced and boilers set
Bathroom plumbing work continued, insulation commenced on site
Sheetrock continued, Door frame installation commenced
Remaining Walls Framed
Spackling commenced on site
Remaining Framing completed, door frames installed
Ductwork connected through to roof
Mechanical room slab and equipment pads poured
Lighting delivery on site
HW CW piping continued on the first floor
Door Frame installation and delivery
Sheetrock installation commencing on site
Concrete pads poured in Mechanical rooms and bathrooms
Sheetrock commenced throughout site
Underground Plumbing complete on ground floor.
Prep, Gravel Infill, and wire mesh complete for Mechanical room slab.
Gravel infill and prep completed for bathroom floor slabs.
Wall framing continued on second floor. Rough electrical continued second floor.
Ceiling grid and soffit framing commenced on second floor.
Domestic Hot Water and Cold Water piping commenced.
Mechanical piping continued on first floor.
Rough Sanitary Piping completed for first floor bathrooms.
Plumbing sanitary rough in continued for bathrooms on ground floor
Plumbing sanitary rough in continued on ground floor
Trenching continued on ground floor
Hydronic piping commenced on ground floor
Masonry wall construction on ground floor
Sanitary/drain pipe installation on ground floor
Sprinkler main installation on first floor
Sanitary piping in bathrooms on first floor
Sprinkler pipe installation on second floor
Wall in room 107 demolished
CMU wall separating urologist’s office and bathroom demolished
Knocking out door headers & installing concrete lentils
Failing ceiling in existing room 62 removed.
Framing
New door opening being cut into walls.
Delivery of Ductwork
Framing on second floor completed.
Formwork and rebar for concrete pad commenced
Glen Ridge BOE – Central School
Glen Ridge, New Jersey
Construction Manager's Status Report (January 2, 2019)
A. Activities performed during the 12/17/18 to 1/2/19.
B. Activities projected for the 1/3/19 to 1/17/19