Daily Work Summaries

Daily summaries will be updated to this page as soon as possible. Please refer to the weekly meeting minutes for detailed work status.

Saturday 7/15/17 and Sunday 7/16/17

In the high 70s with occasional shower

Saturday

* Thomas Mechanical ( 10)

* Sheetmetal Specialties ( 10)

* Demo ( 4)

* Norway Electric ( 10)

* ReArch ( 1)

TOTAL 35


Sunday

* Environmental Foam ( 3)

* Labor (2

ReArch ( 1)

TOTAL 6


Just more of the same from Friday

Friday 7/14/17

68° dry and sunny, then rain

* DecTam ( 21) Took the test on the 1966 wing - Should get results tomorrow

* ReArch ( 4 )

* Rotax (2)

* Reliance Steel ( 4) Seeing roof top steel frames

* Cut Right Concrete ( 3)

* Lacaillade Masonry ( 2)

* Bruso Contracting ( 3) Installing windows

* Environmental Foam ( 4)

* Future Floors ( 4)

* Dennis White Interiors ( 7 )

* Finishing Touches ( 2 )

* Sheetmetal Specialties ( 7)

* Tri-state Sprinkler ( 2)

* Thomas Mechanical (10)

* Alliance Mechanical ( 3 )

* Norway Electric ( 10)

Thursday 7/13/17

72° sunny

* DecTam ( 21) We should be ready for a test on the 1966 wing tomorrow

* ReArch ( 5)

* Cut Right Concrete ( 5)

* Vermont Concrete Cutting ( 2)

* Rotax (3)

* SD Ireland (2) Pouring HVAC pads

* Lacaillade Masonry ( 2)

* Reliance Steel ( 3)

* Window installers (5)

* Future Floors ( 5)

* Dennis White Interiors ( 6)

* Finishing Touches ( 2 )

* Sheetmetal Specialties ( 7)

* Tri-state Sprinkler ( 4)

* Thomas Mechanical ( 9)

* Alliance Mechanical ( 4)

* Norway Electric ( 10)

TOTAL 95

All trades doing mostly the same as yesterday

Wednesday 7/12/17

75° mix of sun and rain

* DecTam ( 21) Now that Kalediscope is done I had them clean the floor on the south side with Simple Green and on the north side with Pinesol as Greg did not like the odor left from the abatement process - It was decided to use Simple Green on future areas and not Pinesol

* ReArch ( 5)

* Omega Site ( 2)

* Cut Right Concrete (5)

* Vermont Concrete Cutting ( 2)

* Rotax ( 3)

* Lacaillade Masonry ( 2 )

* Reliance Steel ( 3) Installing plates on the roof for roof top equipment

* Future Floors ( 5)

* Dennis White Interiors ( 6)

* Finishing Touches ( 2 )

* Sheetmetal Specialties ( 7)

* Tri-state Sprinkler ( 4)

* Thomas Mechanical ( 9)

* Alliance Mechanical ( 4)

* Norway Electric ( 10)

TOTAL 90

All trades are doing mostly the same as yesterday with the exception of Lacaillade Masonry who are working on the front entry columns

Tuesday, July 11

78° Mix of sun and rain

* DecTam ( 21)

* ReArch ( 5)

* Rotax (4)

* Lacaillade Masonry ( 3) Pointing brickwork

* Reliance Steel ( 2)

* Bruso Contracting ( 3 )

* DennisWhite Interiors ( 5 )

* Future Floors ( 5)

* Finishing Touches ( 2 )

* Sheetmetal Specialties ( 5)

* Tri-state Sprinkler ( 4)

* Thomas Mechanical ( 12)

* Alliance Mechanical ( 5)

* Morway (10)

TOTAL 86

All trades are doing mostly the same as yesterday

Monday, July 10

75° Mostly dry and sunny

* DecTam ( 21) - Working in the 1996 wing - Kaleidoscope is done and the protection is being removed - Once the 1996 building is cleared the crew will be split to do Mosaic and Library/IT at the same time and then Health Office -

* ReArch ( 4)

* Demo ( 10) - Mostly insulation demo

* Lacaillade Masonry (3) brick pier work

* Reliance Steel ( 2) Roof top steel for HVAC units

* Bruso Contracting ( 3) Installing windows

* Future Floors ( 5 ) units Grinding floors

* Dennis White Interiors ( 6) -Metal.stud framing has started

* Finishing Touches ( 2 ) Wall prep in the pod hallway

* Thomas Mechanical ( 13) Installing new heating piping mostly

* Sheetmetal Specialties ( 6) New ductwork in the lobby area and Auditorium

* Alliance Mechanical Controls (5) Roughing in

* Tri-state Sprinkler ( 4) Roughing in

* Norway Electric ( 10) Rough-in

TOTAL 94

Friday, July 7

68° sunny and dry

* DecTam ( 22) working in the 1966 building, both floors - Hoping to have Kaleidoscope passed on Friday

* ReArch ( 3 first shift and 1 on second)

* Demo ( 16)

* Omega Site (1) - Digging an electrical trench and installing stone at the HVAC condensers units on the ground

* Vermont Concrete Cutting ( 2) -Cutting the slab in the boiler room

* Lacaillade Masonry ( 3) - Did a sample power wash and sample masonry grout

* Environmental Foam ( 4) - Roof of the main lobby and adjacent hallway

* Future Floors ( 5) Grinding floors

* Alliance Mechanical ( 3)

* Thomas Mechanical ( 10)

* Pipe insulation (1)

* Sheetmetal Specialties ( 4)

* Tri-state sprinkler ( 4)

* Norway (10)

TOTAL 88

Generally everyone is rebuilding except for the demo crews - Demo is mostly insulation removal at this stage

* We had an HVAC meeting in the morning planning for the next couple of phases about the above-the-ceiling spaces -

* There was an afternoon job meeting

Wednesday, July 5

72° sunny

* DecTam (22) - They have the Kaleidoscope rooms protected and the north wing upper floor of the 1966 wing - ATC completed a preliminary review of their protection methods and all was OK - Their big trailer is due tomorrow and they will start abatement - Kaleidoscope abatement should be done tomorrow and air tested Friday

* ReArch ( 4)

* Demo ( 15) Mostly insulation demo with dome bathroom demo

* Lacaillade Masonry ( 2 ) Did a sample power washing of brickwork in the courtyard -It can be examined after tomorrow's meeting

* Environmental Foam ( 5) Spraying at the front offices and A pod

* Future Floors ( 5) grinding the floor in C pod

* Alliance Mechanical ( 4) working on controls

* Thomas Mechanical ( 10) running new piping

* Sheetmetal Specialties ( 5 ) Working on both demo and new

* Tri-state sprinkler (3) Installing piping

* New England Air ( 1) Cleaning existing ductwork

* Norway Electric ( 10 ) A mixture of demo and new

Total 88


Tuesday, July 4

76° Dry and sunny - Independence Day

* Jim Hoag from Re-Arch was here with the spray foam folks until about noon

* A test run has been done on removing the floor mastic in the pods - It looks like the surface will be ground first followed by bead blasting

Monday, July 3

75° Sunny

* ReArch ( 1)

* Demo ( 14)

* Environmental Foam ( 8)

* Future Floors (2)

* Sheetmetal Specialties ( 4)

* Thomas Mechanical ( 11)

* Norway Electric ( 10)

The trades were doing essentially the same scope of work as Friday with the exception of Future Floors who were here starting on floor prep

* We had ATC here on Friday providing consultation on better isolating the work areas from staff areas - All of their recommendations have been followed and we will have them here Wednesday to check compliance with recommendations

Saturday, July 1

74° sunny

* There was a large demo crew here removing the fiberglass an cellulose of the pod ceilings, exposing the sprayed sections of attic ceiling

Friday, June 30

68° A mixture of showers and sunny spells

* DecTam has 12 here and may have more this week if they get a job finished in Northfield, VT - If not, they will be here Wednesday

* ReArch ( 5)

All trades are doing demo in the pods except for the tin - knocker and plumber have just started to install new

* Demo ( 22)

* Reliance Steel ( 2) Laying out for steel at roof penetrations

* Environmental Foam ( 7 )

* Thomas Mechanical (12)

* Sheetmetal Specialties (8)

* Morway Electrical (11)

Wednesday, June 28

68° sunny

* DecTam ( 7 ) Doing prep work in the 1966 building -The extra people due tomorrow may be delayed a day or two as the person issuing licenses for them is out sick this week

* All the trades are still in demolition mode except for Environmental Foam who have started the spray foam operation in the attic at the C pod

* ReArch ( 4)

* Demo (22)

* Casella (1)

* Reliance Steel (2)

* Environmental Foam (7)

* Thomas Mechanical (12)

* Sheetmetal Specialties ( 8)

* Norway Elect ( 11)

Monday, June 26

68° dry and sunny

There was a changed condition in the kiva on the second floor of the 1966 building that will be discussed at the Facilities meeting

* DecTam (7) - They started setting up on the uppper level of rhe 1966 building and expect 15 more workers by Wednesday

All the trades are doing demo in the pods and the lower level east/west hallway of the 1966 building

* ReArch (3)

* Cut Right Demo (14)

* Rotex demo (6)

* Thomas Mech (12) -In addition to demo they are installing plumbing valves where pipes are cut so as to maintain services

* SSI (8)

* Norway Elect (10)

Environmental Foam and sprinkler due tomorrow

Total 60

Saturday, June 24

72° Showers early

* ReArch (1)

* Demo crews (10) - Working in the same areas as yesterday

* Plumbing crew (12) - Same as yesterday

Friday, June 23

76° numerous heavy showers throughout the day

* The PCBs were bid - A matrix of the results will be sent to the Owner's team under separate email

* ReArch 4

* Demo crews 25 - Removing ceilings and flooring in pods and the lower level hallway of the 1966 building

Plumbers 12 - Removing plumbing fixtures and piping in the pods and lower level hallway of the 1966 building - They have removed most of the required plumbing fixtures in the upcoming abatement areas

Duct 8 - Removing ductwork in the pods and lower level hallway of the 1966 building

Elect 8 - Removing wiring, devises and boxes and disconnecting mechanical items as need throughout the pods and lower level hallway of the 1966 building


Thursday, June 22

73° dry and sunny

* We had a job meeting today

* Morway Movers (7) All of the pods have been moved and 90% of the abated areas are moved except for the Mosaic wing, which they will finish tomorrow

* ReArch Management (3)

* Demo two crews (16) - Removing ceilings in the corridor and walls in the 3 pods

* Thomas Mech. (10) - Removing plumbing and piping in the hallway and pods

* SSI Duct (6) - They removed most of the attic mechanical equipment before today - Now on hallway and pod ductwork

* Norway Electric (8) - Tracing circuits and demo in the hallway and pods

Total person power 43