All plywood joints have been caulked. Some caulking is needed on the casing around the window yet.
The larger roof, with the short eaves, requires every last shingle in the five purchased bundles. This does not allow for mistakes. Consider purchasing an extra bundle for the next house.
A 1/2" shingle overhang of the fascia was targeted for each side of the house.
Care was taken when it was necessary to walk and move on the hot shingles to prevent damage to the shingles.
Exterior caulking was completed. For the next house, more instruction on how to do caulking that looks good is necessary.
All roof sheathing was installed with 3" screws. 1/8" spacing was allowed between all panel edges. Screws were placed on 6 in centers on the edges, and 12" in the field.
The drip edge on the lower edge of the roof was installed and nailed to the roof sheathing. Corners were cut so that it could be bent up about 6" at each rake. The framing nailer and 8D siding nails were used to secure the drip edge to the sheathing.
15# asphalt roofing paper was installed (four courses) so that at least 6" of overlap were achieved. The first course was on the low side of the roof.
Drip edge was then cut and installed on top of the roofing paper along each rake edge. This piece was simply cut the length of the rake edge and is not bent around either corner. The framing nailer and 8D siding nails were used to secure the drip edge to the sheathing.
The interior casing was installed around the door.
The window jamb was shimmed in place and then nailed with 2.5" long 15Ga finish nails.
Interior casing was started on the window. When the first piece was cut long but then nailed in place, the Fein multitool needed to be used to trim it to its proper length.
Much of the caulking of all seams and joints were completed on the outside of the house.
Two pallet jacks and the school's forklift were used to move the shelter out from under the breezeway cover to allow for the installation of the roof insulation, sheathing, and shingles.
All rigid insulation was installed. Insulation was installed without gaps, and 2.5" long, 7D HDG nails were used to tack the insulation in place.
The first piece of roof sheathing was installed. Sheathing was attached using 3" screws placed at 6" centers on the edges, and 12" in the field along rafters. Roof sheathing will be gapped 1/8" along all edges to account for plywood swelling should it become moist and absorb water.
All exterior trim, primarily on the rear wall, was installed, including window trim. Trim around the heat pump will be installed at the house's final destination -- the heat pump is not here yet so final fit-up would not be possible.
The brick molding, which was left off the door by the manufacturer, was installed. The 15Ga nail gun was used with electrogalvanized finish nails.
A window was discovered broken this morning with a pin-hole chip in it. The sealed argon space has been compromised. Smith Glass will be out on Tuesday to provide an estimate to replace the stationary half of the window. It is believed that weed eaters from grounds maintenance activities threw a rock at the window.
All eaves and soffit enclosures were finished. All Hardi has been installed. Soffit material for the side walls was all from off-cut pieces used previously on the house.
We determined that the framing nailer, shooting 2-3/8" x .113 ring shank HDG nails actually worked better than the coil siding nailer with the Hardi. The downside of course is that these nailers are heavier.
Trim board installation has been started. The vertical trim board on the porch near the door was caulked as well because this would not be possible once the exterior brickmold (that was left off the door by the manufacturer despite ordering it attached) is installed by hand.
The last sheet of Hardi cedarmill siding was installed on the structure on the tall side of the porch.
The first piece of Hardi cedarmill material was installed to enclose the rear roof overhang. There were no pieces long enough that remained to enclose the rear roof eave in one piece.
Three more pieces of Hardi siding were cut and installed -- one on the rear wall, and two in the porch area.
Fascia on both sides of the house, as well as the fly rafter in the back were installed.
Blocking was installed on on the inside of the fascia at the rear of the house in preparation for eave enclosure.
The last sheet of Hardi cedarmill siding was installed on the tall side of the house.
One sheet of Hardi cedarmill siding was installed on the rear wall, and one on the front wall of the house.
Additionally, the window jamb was cut and nailed together for the interior.
The door was installed prior to the siding on the porch so that the siding can be cut to fit the door. Deck boards were removed so that sill flashing could be installed at the bottom of the door. The hinge side of the door was attached first and the hinge jamb was shimmed so that it was vertical. Then the latch side of the jamb was shimmed to maintain a straight reveal between the jamb and the door. Caulking was placed beneath the threshold of the door.
Two more panels were installed on both the long and short sides walls. The first two panels on each wall, starting from the rear, can be full width. The last two must be cut to width to match stud location.
Two sheets of cedarmill hardi panel siding were installed on the short side of the shelter, and one on the tall side. Power shears were used to cut the hardi panel to minimize the dust. Jigs were used to support each panel at the bottom and assure the alignment of the bottoms of each panel.
The opening for the heat pump and the door were both flashed on 5/19.
Besides finishing the house wrap on the porch, eave blocking at the rear of the house was installed.
Additionally, the front fascia board was installed.
Most of the WeatherSmart house wrap was installed. There is still just a little to do on the porch area of the house.
The window was installed and flashed.
Home Insulation was here and blew insulation in all the wall cavities. Batt insulation was installed in the roof do to the limited clearance above the roof of the tiny shelter.
All rough electrical work was completed today by Northside Electric. When exterior siding is installed, holes will be provided in the siding and the wiring for the porch light and the electrical plug in the back will be made.
The only thing completed today was the porch decking. It is now finished.
Sheathing was cut out from the window and the heat pump openings using a trim router and a flush-cut bit.
The final two pieces of interior sheathing was installed. All remaining screws were installed on the sheathing.
All the blocking at the eaves was completed. Gaps in the rafters over the front wall were sealed with duct tape in preparation for insulation.
Deck boards were cut. End screw positions were pre-drilled. Some boards were installed.
Three more pieces of interior sheathing were installed.
Eave blocking was completed on the short side of the house.
Four more pieces of 1/2" interior plywood sheathing was installed
More blocking was completed.
Two more pieces of ceiling sheathing on the interior were installed.
All hurricane tie installation was finished.
Blocking for ceiling sheathing was installed on the rear wall.
Two 4x4 lookouts to support the rear roof overhang and fly rafter were installed.
Blocking at the eaves was started. This blocking helps with roof rigidity, provides a nailing surface when the eaves are enclosed, and will provide a barrier for roof insulation.
The first piece of interior ceiling plywood was installed. This required five people -- four to hold, and one to fasten it in place.
Plywood attachment to the rear wall, bottom course was completed.
Rafter installation was completed except for the installation of four hurricane ties. The tail of two rafters were cut too short and needed to be replaced.
The 18" long Simpson LSTA straps were installed at the double top plates in all four interior corners of the living space.
The double top plate was cut and installed on the front and rear walls, finishing the framing of these walls.
A new piece of plywood was installed on the rear wall. Only two screws installed however.
All the birds mouths on all of the rafters have been cut.
The rafter on the rear wall was cut and installed. It still needs hurricane ties.
String was run from the end of each of the tails of the front rafter to the rafter on the back wall. These strings will be used to align all rafter tail cuts as they are installed.
Two additional rafters were fully installed. Each of these received two toed screws connecting each rafter end to the double top plate of one of the side walls. One more rafter has its tails cut and needs to have hurricane ties installed.
The framing of the front and rear walls are almost complete. All that remains is installing the double top plate for both walls.
The front rafter was cut and installed.
The birds mouths for three other rafters were cut and are ready to have their tails cut.
Hurricane tie installed connecting the front rafter to the right side wall. A screw was used in one hole because the top plate was splitting.
Also, when the jack studs were cut for the front door, the bottom plate thickness was not subtracted. Therefore, an additional 2x4 was installed below the header to take up the extra 1.5" height of the rough opening.
One stud, the king studs and jack studs for the door, and the door header were installed. Screws were placed through the top plate. Stud bottoms were toe-screwed to the bottom plate. After installation, it was realized that the bottom plate was not taken into account when the jack studs for the door were cut. The header will need to be lowered by 1-1/2" -- likely by adding a third 2x4 to the underside of the header.
Four studs were cut and installed on the rear wall. Studs were screwed through the top plate, and toe-screwed with three screws each to the bottom plate.
Screw installation was finished on the first course of the plywood sheathing on the short side wall.
A double top plate was added to both side walls.
The bottom plate for both the front and rear walls were installed and layouts completed. End studs were cut, and the top plate was installed for each wall.
Final leveling of the floor was completed using a laser level.
Studs were cut for the short wall.
The first course of plywood was placed on the square tall side wall. This wall was then placed on the floor, braced plumb, and then screwed to the floor using 3" screws.
The short side wall was nailed together. Pilot holes were placed on the ends of the plates and 3" screws were used on the end studs to prevent plate splitting.
The short side wall was squared, the first course of interior plywood sheathing was installed, the wall was set in place, braced plumb, and then screwed to the floor.
Fastening the floor plywood to the floor framing was finished.
Spacer pieces were screwed into place that will support the side walls in the front porch area.
A builders level was used to level the floor in place so that walls, when installed, could be made plumb relative to the floor.
The tall wall was assembled using framing nails, and time was spent making this wall square.
The floor framing was relocated and placed on its skids.
The diagonals of the frame were measured to insure they were the same length to make sure the frame was square.
All joist hangers were installed between each floor joist and the rim joist.
A hurricane tie was installed connecting each skid with each floor joist and rim joist.
The diagonals of the frame were measured and the frame adjusted to make sure it was square.
The 1" rigid insulation was placed on the frame and tacked in place with 8D hot-dipped galvanized (HDG) nails. They were placed so the long edge was parallel to the floor joists. This insulation is only being placed beneath the inside space of the tiny home. The front three joists will be the front deck of the home.
The 3/4" tongue& groove plywood floor sheathing was installed over this foam oriented at right angles to the direction of the floor joists. The seam between the two courses of plywood was staggered. The plywood was attached to the floor and rim joists using 3" screws. Each piece of plywood was fastened with screws at 6" centers on the edges, and 12" centers in the field.
Materials were unstacked and unpacked.
Two long side rim joists were cut to length, and the joist lay-out was completed.
All floor joists were cut to length, and skid locations marked.
All rim and floor joists were nailed together with 3" nails.
The four A35 framing angles were installed in the four inside corners.