16 Year Bond of 21,590,000
Projected: $14,257,635
Net: $12,831,872
(10% removed for financial contingencies)
(25% total contingency - 15% construction added into costs, 10% removed from the net monies)
HS Renovation - $5,859,275
HS Gym Renovation - $1,862,479
HS West Corridor Renovation - $199,507
Football Stadium w Turf - $2,847,960
Football Field Concession/Toilets - $ 939,326
Intermediate Kitchen/Dining Area - $1,088,714
Portable Classroom - $75,000
Total $12,872,261
Date Bonds Voted Years Millage Rate Contingency Net $ Tax Increase
3/1/23 $21,590,000 16 26.5 $0 $14,257,636 5.95%
Proposed bond raises millage from 20.96 to 26.5 (.75 increase from last bond issue)
This will raise property taxes 5.95%, so $5.95 per $100 in taxes
● Ex. $1000 in property taxes will see $59.50 increase/year
● $5.15 per $100 to bring up to original 25.75
● $0.80 per $100 to add additional 0.75 mills to bring to 26.5
Information Below was posted on 11/14/2022 at https://www.clevelandtigers.com/proposed-bond-projects-voting-on-10th-day-of-january-2023-legal/ in accordance with the bond transparency act of 2017.
to renovate, repair, remodel, furnish, and/or acquire improvements at the High School Building $12,830,000.00
to construct, equip, furnish, and/or acquire a new Football Field $7,300,000.00
to construct, equip, furnish, and/or acquire a new Intermediate School Cafeteria $1,460,000.00
TOTAL: $21,590,000.00
As of the 10th day of January, 2023, Independent School District No. 6, Pawnee County, Oklahoma, has 2 General Obligation bond issue(s) outstanding:
$2,545,000 Building Bonds of 2020, dated February 1, 2020 ($1,300,000 outstanding in principal as of the 10th day of January, 2023); and
$2,545,000 Building Bonds of 2022, dated March 1, 2022 ($2,545,000 outstanding in principal as of the 10th day of January, 2023).
The School District has $3,820,000 in unissued building bonds authorized at an election held on the 12th day of January, 2016. These bonds will be used to complete the constructing, furnishing, equipping, and/or acquiring of an addition at the primary elementary school, renovations at the Vo-Ag and Alternative Education Building; and renovations, repairs and/or remodeling at school sites, as needed.
2020 Issue
Construct, furnish, equip, and/or acquire improvements at the high school to
include, but not be limited to: HVAC equipment $1,500,000.00
Construct, furnish, equip, and/or acquire a new track to include, but not be limited to: site work, asphalt, track surface, concrete footings, sidewalks and track
equipment $945,000.00
Renovate, repair and/or remodel school sites, as needed $100,000.00 2022 Issue
Construct, furnish, equip, and/or acquire improvements at the middle school to include, but not be limited to: HVAC equipment, insulation, roofing, ceiling tiles,
paint, and flooring $1,855,000.00
Construct, furnish, equip, and/or acquire improvements at the intermediate elementary school to include, but not be limited to: stage curtains, sound system,
playground shades, and turf $115,000.00
To acquire and install fencing around the track, baseball field and softball field $170,000.00 To acquire and install energy management control systems throughout the district $305,000.00 Renovate, repair and/or remodel school sites, as needed $100,000.00
Site Addresses:
Administration Building, 600 N. Gilbert, Cleveland, Oklahoma High School, 323 N. Gilbert, Cleveland, Oklahoma
Middle School, 322 N. Gilbert, Cleveland, Oklahoma
Intermediate Elementary School, 705 N. Swan Drive, Cleveland, Oklahoma Primary School, 300 N. Gilbert, Cleveland, Oklahoma
Bus Barn, 1300 N. Crestview, Cleveland, Oklahoma Event Center, 324 N. Gilbert, Cleveland, Oklahoma