March 13 - Bond Passage
April - November Plan and design projects for State Review
July
August
September
October Begin Chambers Field & Track Replacement (Est. to begin first week of Nov.)
November
December
January
Completed Tasks: (as of Jan. 12)
1. Construction Fencing installed securing the site
2. Demolition of draining systems to be replaced
3. Removal of track surface
4. Demolition of batting cage
5. Removal of large ash tree on southeast end of track
6. Replacement of Fencing along Willow Avenue side of track
Tasks Currently Underway
1. Replacing damaged draining systems
2. Replacing concrete curbing around track
3. Scoreboard foundation & structure
What to Expect:
January 2019- All Complete
· Order turf, padding & infill
· Complete scoreboard foundation & structure
· Additional chain link fencing
February 2019- All Complete
· Removal of existing turf
· Re-grading of subsurface gravel
· Delivery of padding, turf & infill
· Scoreboard installation
· Additional chain link fencing
March 2019- All Complete
· Installation of padding, turf & infill
· Installation of running track
· Installation of removable netting
April 2019
· Installation of padding, turf & infill - Complete
· Installation of running track - Final Stages will be complete by end of June
· Installation of removable netting - Complete
· Delivery of field equipment- Complete
· Landscaping & paving - Complete
· Punch list
Additional Flood mitigation pumps - installed - Complete
April 2019
- Bids received - ** Note GC Bids higher than anticipated and were rebid
May 2019
- Bids received - Bids were awarded at the May 21st BOE meeting a list outlining scope of work (including reduction of work) will be sent out to the community
June 2019
- Library Project - Begins June 10th - Scheduled for completion end of September
- Chambers Field and Track project - Completed - opened August 2019
- Flood Pumps Completed and operational
July - August
Update as of Nov. 1, 2019