From 03–04 March 2026, the 220 kV Singhigaon–Dhamdum feeder (Bay-206) was taken under the Annual Maintenance Plan (AMP) 2026 to improve the reliability and safe operation of the transmission line. The main focus of the maintenance was to investigate and rectify a long-standing **B-phase circuit breaker closing failure and pole discrepancy issue. During the inspection, a loose negative DC return connection at Terminal Block X2-42 was identified and corrected, which restored normal operation of the R-phase and Y-phase breaker poles. Further investigation inside the breaker mechanism revealed that the B-phase cross-roller plunger limit switch (-L4) had been damaged and incorrectly wired to a normally open contact, preventing automatic closing of the B-phase. The wiring was corrected to the proper normally closed terminal, which successfully restored synchronized closing of all three breaker poles and eliminated the unsafe manual operating workaround previously used. In addition, insulation resistance testing of the surge arresters was carried out, confirming that the R and Y phases are in healthy condition, while the B-phase arrester showed comparatively lower insulation values, indicating ageing and requiring close monitoring and future replacement. Overall, the maintenance activities successfully restored reliable breaker operation and improved the operational stability of the 220 kV Singhigaon–Dhamdum transmission line.
From 24–26 February 2026, the 220 kV Malbase–NIP (Samtse) feeder (Bay-203) was successfully taken under the Annual Maintenance Plan (AMP) 2026 to improve the reliability and operational safety of the transmission line. During this maintenance period, the R-phase Capacitor Voltage Transformer (CVT) was replaced due to continuous oil leakage from the secondary terminal box, and a serviceable terminal box from the old unit was reused to ensure proper sealing and avoid delays. After installation, insulation resistance, winding resistance, and voltage ratio tests were conducted, confirming that the new CVT is in healthy operating condition. In addition, a critical defect was detected in the Y-phase lightning arrester (LA) bottom stack, which showed extremely low insulation resistance, indicating internal failure; the defective stack was therefore replaced using a Hydra crane, restoring the insulation strength of the arrester assembly. The B-phase LA was assessed and found acceptable for short-term operation, though replacement is recommended in the next maintenance cycle due to ageing indications. Some current transformer (CT) diagnostic tests were postponed due to safety concerns related to busbar clearance and high-voltage induction. Overall, the maintenance activities were completed successfully, significantly improving the protection reliability and operational stability of the 220 kV Malbase–NIP transmission line
On 05.03.2026, the 220 kV Malbase–Singhigaon transmission line was commissioned for the Annual Maintenance Plan (AMP). Based on the tests conducted, the R-phase CVT was found to be technically sound and suitable for continued service, although the absence of Y and B phase CVTs requires the protection scheme to rely on alternate voltage sources such as Bus CVTs to maintain directional and distance protection functions. The surge arrester bank for the line has been fully restored following confirmation of internal dielectric failure in the original R-phase unit; a new OBLUM three-stack surge arrester assembly has been installed and all phases now meet the required insulation resistance standards for 220 kV operation. The Y-phase Current Transformer (Bay-206) is in partial compliance, as cores 1, 2, and 5 meet manufacturer specifications while Core-4 failure poses a potential risk to the protection scheme. Additionally, the CVT voltage ratio test conducted with 244 V primary injection produced consistent secondary readings of 0.144 V across protection and metering cores (approximately 18% deviation from the calculated 0.122 V), which is attributed to normal CVT behaviour under low-voltage testing and does not indicate any defect.
On 10–12 February 2026, a team from the Transmission Control Centre Department (TCCD) visited Malbase Substation to resolve a long-standing issue in the Tala Line tripping circuit under the 400 kV one-and-a-half breaker (1½ CB) protection scheme. The problem involved the Tie Breaker (405) failing to trip simultaneously with the Main Breaker (404) during protection operations, which posed a serious operational risk as fault current could propagate to adjacent feeders. The team conducted a detailed technical investigation including verification of protection schematics, inspection of control and protection wiring, continuity checks, and functional testing of relays and annunciation circuits. Over three days of systematic troubleshooting, the team successfully rectified protection wiring discrepancies, corrected tripping logic coordination, and restored proper annunciation and indication functions. After final testing, both breakers were confirmed to trip simultaneously under simulated fault conditions, restoring the integrity and reliability of the protection scheme. The work was led by Chief Manager Chophel, with Executive Engineers Sonam Kuenzang Jigme and Kezangla, and Junior Engineer Phurba Gyeltshen. Additionally, on 11 February 2026, the Chief Manager conducted a technical training session for engineers, Malbase staff, and CST OJT students, covering key protection schemes such as overcurrent, earth fault, distance, differential, and line and transformer protection, which significantly enhanced the technical knowledge and operational confidence of the participants.
On 05.02.2026, as per the Annual Maintenance Plan (AMP) approved by BPSO, a one-day maintenance program was successfully carried out on the 220 kV Malbase–Singhigaon feeder. The maintenance team commenced the work by isolating the bay equipment to facilitate the required testing and inspection.
Insulation Resistance (IR) testing was conducted on the 198 kV surge arresters for R, Y, and B phases. During the test, the R-phase surge arrester was found to have a low insulation resistance value, below 1000 MΩ, which is not within the permissible limit. Consequently, the defective R-phase surge arrester was replaced with a new surge arrester arranged from Singhigaon Substation.
Further, the secondary winding resistance tests of the Current Transformer (CT) and Capacitive Voltage Transformer (CVT) were carried out and found to be normal. The insulation resistance tests of the CT and line CVT were also performed and CVT Voltage Ratio test has been carried out satisfactorily. All planned maintenance activities were completed as scheduled, and the one-day maintenance program concluded successfully, ensuring the reliability and safe operation of the feeder.
On 23 January 2026 at 11:00 hours, the Remote Desktop connection between Malbase and Singhigaon Substations was unexpectedly lost, resulting in the inability to access the Singhigaon SCADA system from Malbase Substation.
Root Cause Analysis
Initially, all Western region RTUs under BPSO were configured to report to the Malbase Substation, and the associated communication infrastructure (MPLS-TP) was designed accordingly.
Under the current project scope, the RTUs are required to report simultaneously to the Main Control Centre (MCC) located at the new DGPC building, Babesa, and to the Jigmeling Backup Control Centre (BCC). On 23 January 2026, BPSO migrated the RTU service of Singhigaon Substation to the MCC. Subsequently, on the following day, site officials reported a loss of data communication between Singhigaon Substation and Malbase Substation. Due to the absence of a clearly defined data reporting architecture, immediate fault isolation and resolution were not possible.
Following multiple rounds of coordination and technical discussions between BPSO and site officials, it was confirmed that data reporting to both the BPSO Control Room and Malbase Substation was being routed through a single Ethernet link from the RTU switch to the MPLS-TP equipment (Port No. 1-5-1). Consequently, upon migration of the service to the MCC, data reporting towards Malbase Substation was disrupted. As an interim corrective measure, BPSO reverted the configuration to the previous setup, thereby restoring data reporting.
Recommendations
1. It is recommended that separate physical ports from the RTU switch be terminated to the MPLS-TP equipment for independent data reporting paths to the BPSO Control Room and the Malbase Substation. This will ensure redundancy and prevent service interruption during future migrations or configuration changes.
2. Furthermore, the lack of a clearly defined Standard Operating Procedure (SOP) for RTU data migration and reporting architecture has contributed to the occurrence of this issue. It is strongly recommended that a comprehensive SOP be developed and implemented to avoid similar incidents in the future.
On 24 January 2026, a planned shutdown of the 66 kV Bhutan Concast Feeder was executed by the Construction Project Office (CPO), Phuentsholing, to facilitate critical construction, testing, and commissioning activities associated with the integration of a newly constructed double-circuit 66 kV transmission line at Singhigaon Substation. The shutdown was carried out in accordance with power system operational and safety protocols to ensure secure working conditions for personnel and to prevent any risk to the existing network infrastructure.
During the shutdown period from 09:42 hours to 17:04 hours, the 66 kV Bhutan Concast Pvt. Ltd. and 66 kV Druk Wang Alloys Limited feeders experienced interruption of power supply. The total outage duration was calculated to be 7 hours and 22 minutes. Both industrial consumers are connected through a radial network configuration, and therefore, no alternative supply path was available during the shutdown window. This operational constraint highlights the inherent vulnerability of radial systems in comparison to meshed or ring network configurations within high-voltage distribution systems.
The primary objective of the shutdown was to complete the cable termination, testing, and integration works for the second circuit of the newly constructed double-circuit transmission line at the Singhigaon end. The work scope involved the installation of high-voltage cable terminations, rectification of identified technical deficiencies in the cable system, and verification of electrical and mechanical integrity of the termination assemblies. These activities were mandatory prior to tapping the second circuit from the existing 66 kV Bhutan Concast Feeder, ensuring compatibility and stability of the interconnected network.
The development of the double-circuit transmission line was implemented in a phased manner. The first circuit was successfully completed and test-charged on 03 December 2025 at 11:16 hours, supplied from the 66 kV GIS Spare Feeder at Singhigaon Substation. The successful energization of the first circuit confirmed the adequacy of insulation coordination, protection settings, and system stability under operational conditions. The second circuit, completed on 24 January 2026, is designed to be electrically tapped from the existing Bhutan Concast Feeder following successful completion of all commissioning and testing procedures.
During the shutdown, comprehensive electrical testing was conducted on the newly terminated cable system. This included insulation resistance testing, continuity verification, and high-voltage withstand testing to ensure compliance with applicable technical standards. Mechanical and structural inspections were also performed on termination hardware, gantry connections, and associated fittings to confirm mechanical robustness and alignment. Additionally, earthing boxes were installed and integrated into the substation grounding system, and the continuity of the earthing network was verified to ensure effective dissipation of fault currents and enhancement of personnel safety.
The cable termination works were carried out under the existing Bhutan Concast gantry structure, which forms a critical interface between the overhead line system and the underground cable network. Testing under the live system environment required strict adherence to isolation procedures, permit-to-work systems, and safety clearances to avoid operational hazards. The rectification of cable termination points and associated fittings was completed successfully, ensuring that the system meets the required electrical, thermal, and mechanical performance criteria for long-term operation.
The successful completion of the second circuit termination and associated testing activities represents a significant advancement in the reinforcement of the 66 kV network in the Phuentsholing region. The integration of the double-circuit configuration is expected to enhance system reliability, improve operational flexibility, and reduce the risk of extended outages arising from single-circuit failures. From a power system perspective, the project contributes to improved load-sharing capability, enhanced fault tolerance, and strengthened network resilience, particularly for high-demand industrial consumers.
In conclusion, the planned shutdown of the 66 kV Bhutan Concast Feeder on 24 January 2026 was technically justified and operationally essential for the safe execution of cable termination and commissioning works associated with the second circuit of the double-circuit transmission line at Singhigaon Substation. All activities were completed successfully within the approved shutdown window, and the system is now technically prepared for final integration of the second circuit into the existing feeder network. The project demonstrates a systematic and technically sound approach to transmission system expansion and substation infrastructure development within the regional power system.
On 21 January 2026, a farewell programme was hosted at Malbase Substation to honour two outgoing colleagues—Mrs. Susmita Tamang, who will be proceeding abroad, and Mrs. Sangay Yuden, who has been transferred to the TOMS Division Office. The event was coordinated by Ms. Tshering Yangdon and organized with warmth and gratitude by the Malbase team.
The programme was attended by the Substation Head, shift operators, security personnel, and guests from the Division Office, including Mr. Namgay Dorji (Section Officer), Ms. Tshering Yangden (Engineer), Mr. Kinley Tshering (Engineer), and Mr. Samten Wangchuk (Civil). The presence of seven CST OJT students further enriched the gathering, reflecting the inclusive and supportive culture of Malbase Substation.
The farewell began with words of wisdom and guidance from the Substation Head, followed by a heartfelt address from Mr. Namgay Dorji, who shared his appreciation and best wishes for the outgoing colleagues. The programme continued in a warm and joyful atmosphere, complemented by a simple dinner, refreshments, and a musical session, allowing everyone to celebrate the moments shared together.
This farewell was not just a formal occasion, but a moment to reflect on the dedication, teamwork, and positive spirit that Mrs. Susmita Tamang and Mrs. Sangay Yuden brought to Malbase Substation. Their contributions, professionalism, and kindness have left a lasting impression on the team, and their absence will surely be felt.
On behalf of the entire Malbase team, we extend our deepest gratitude and heartfelt wishes to both our colleagues. May your future journeys be filled with new opportunities, success, good health, and happiness. As you move on to the next chapters of your lives, please know that you carry with you our respect, fond memories, and best hopes for a bright and fulfilling future. You will always remain a part of the Malbase family.
On 16 January 2026, maintenance work was successfully carried out on the 66 kV Bhutan Concast Feeder between 11:00 hours and 13:14 hours to address a strand cut observed on the line. During the shutdown, the R-phase strand-cut jumper at the cable termination was replaced. This rectification restored the mechanical strength of the connection and ensured its full current-carrying capability, thereby improving the reliability of the feeder.
Following the repair, Insulation Resistance (IR) testing of the line surge arrester was conducted, and the results were found to be satisfactory, confirming the integrity of the insulation system. In addition, the earthing system was tested, and the measured earth resistance values were within the permissible limits as per substation standards. This verified the effectiveness of the grounding system and ensured the overall operational safety of the installation.
The feeder was subsequently restored to service after completion of all tests, ensuring safe and reliable operation
On 10 January 2026, the Traditional Archery (མདའ་རྩེད་) Intra-BPC Friendly Match between Thimphu and Phuentsholing was held at the Pasakha Archery Ground, near the Police Station. On this auspicious occasion, the Malbase Substation Head humbly offered a Tshogchang (ཚོགས་ཆང་)—one carton of beer—to the CEO of BPC as a small token of goodwill and a heartfelt gesture to mark the event. The Honorable Directors, along with almost all Managers, actively participated in and attended the match, joining players and spectators in celebrating this traditional sporting event that strengthened unity and camaraderie (མཐུན་སྒྲིལ་དང་མཛའ་མཐུན་). During the first round, the Thimphu team scored 17 points, while Phuentsholing BPC scored 25 points. In the second round, Thimphu scored 25 points, and Phuentsholing BPC scored 0. The match was highly entertaining and vibrant, enriched by traditional dances and songs, making the event a joyful celebration of Bhutanese culture and sportsmanship.
The 220 V DC Battery Bank–I has been successfully restored to service following the installation and commissioning of a new 220 V DC, 400 Ah battery bank on 07-01-2026. This DC battery system plays a critical role in ensuring uninterrupted and reliable DC supply to protection relays, control circuits, SCADA systems, and emergency tripping operations, especially during AC supply failures. The installation and commissioning activities were carried out with the active involvement of shift operators, the maintenance team, and CST OJT students, providing a valuable hands-on learning opportunity alongside practical exposure to substation DC systems. Key activities included battery placement, polarity checks, inter-cell connections, DC bus voltage verification, charger health checks, insulation resistance testing, and load observation to confirm system stability. Bringing the battery bank back into service has significantly enhanced the reliability and resilience of the substation control and protection system, ensuring safe operation of critical equipment and reinforcing the importance of well-maintained DC auxiliary power systems in power networks.
On 05.01.2026, following the Low Oil Level Alarm that operated on 04.01.2026 for 10 MVA Transformer–I (Bay-604) as indicated on the RET670 transformer protection relay, oil topping-up was carried out by the maintenance team in coordination with shift operators. To ensure safe execution of the work and to avoid any inadvertent alarms or protection mal-operations, the transformer was electrically isolated by opening Incomer-I circuit breaker on the LV side and Breaker 604-52 on the HV side at 09:51 hours. After establishing safe isolation conditions, the transformer oil was topped up to the prescribed level. The oil topping-up activity was successfully completed, restoring the oil level within normal operating limits and ensuring reliable transformer operation without further relay alarms or protection issues.
On 27 December 2025 (Saturday), a total of 30 technicians from the National Center for Hydrology and Meteorology (NCHM), representing all 20 Dzongkhags of Bhutan, visited the Class C Meteorology Station at Malbase as part of their ongoing workshop program. The visit aimed to provide participants with practical exposure and hands-on understanding of meteorological instruments, station operations, and data collection processes. During the session, technicians were briefed on weather observation techniques, real-time data monitoring, equipment maintenance, and reporting procedures followed at the station. Officials at the Malbase station shared insights on operational challenges, safety practices, and the importance of accurate meteorological data for weather forecasting, hydrology, disaster preparedness, and public safety. The interaction also encouraged knowledge exchange among technicians from different Dzongkhags, strengthening coordination and standardization of meteorological practices nationwide. Overall, the visit was highly informative and productive, enhancing the technical capacity of participants and reinforcing NCHM’s commitment to improving weather and climate services across the country.
All operators and College of Science and Technology (CST) OJT trainees are currently engaged in the Online Capacity Building Program on “Grid Operational Challenges in View of Energy Transition.”
The global energy transition is transforming power systems far beyond the addition of renewable energy, creating major operational challenges for electricity grids. Despite rapid growth in renewables, fossil fuels still dominate energy supply, while climate change is driving extreme weather, heatwaves, and natural disasters that directly threaten grid reliability. At the same time, next-generation loads such as air conditioning, electric cooking, electric vehicles, green hydrogen, and data centres are causing sharp demand peaks, higher ramping requirements, and increased dependence on power-electronic-based systems. High penetration of inverter-based resources is reducing system inertia and strength, increasing the risk of frequency and voltage instability, as seen in recent large-scale blackouts in advanced power systems. Addressing these challenges requires strong grid codes and standards, robust transmission planning, energy storage deployment, advanced forecasting, digitalization, cybersecurity, and cross-border cooperation to balance reliability, sustainability, resilience, and affordability in the evolving energy landscape. -09.12.2025
On 04 December 2025, two Engineers from the Bhutan Power System Operator (BPSO) visited the Malbase Substation as part of a field familiarization and system study tour. The purpose of their visit was to understand the ground-level operational challenges, review system configurations, and observe the practical aspects of substation operations. During the visit, the Substation Head and Engineers provided a detailed walkthrough of the substation’s functioning. They highlighted key operational challenges, ongoing technical issues, and shared insights into the real-time constraints faced during day-to-day system operation. The team also reviewed the existing SCADA integration, equipment health conditions, protection coordination, and communication link status. This interactive session was immensely beneficial as it helped the visiting BPSO officials gain a deeper understanding of the site realities, strengthening the coordination between the substation team and system operators. Such field visits play a crucial role in enhancing system reliability, ensuring better decision-making, and improving national grid operations. The familiarization tour stands as a positive step toward collaborative problem-solving and efficient grid management.
On December 2, 2025, our team gathered at the Division Office Conference Hall in Phuentsholing for an important coordination meeting led by the Chief Manager of TOMS, P/Ling. Substation Heads, TOMU Heads, and Engineers from different locations came together with one goal: to improve the way we work and manage our systems.
1. Prioritizing Safety Through HIRA
One of the major highlights of the meeting was safety. The Chief Manager stressed the importance of Hazard Identification and Risk Assessment (HIRA) in every substation. Each team was reminded to maintain proper HIRA records to ensure safer and more proactive operations.
2. Smarter Purchase Requisition
We also discussed the importance of submitting only essential purchase requisitions. The idea is simple—focus on what is genuinely required so that resources are used wisely and effectively.
3. AMP vs. APM: Understanding the Difference
Another key topic was the Annual Maintenance Plan (AMP) and Asset Performance Maintenance (APM). The Chief Manager clarified that both cannot be carried out together because APM requires management-level testing tools, which we currently do not have. This clarity helps us plan better for future maintenance activities.
4. Planning Ahead for TAS 2026
The team explored the early planning stages of TAS for 2026, ensuring we are well-prepared for upcoming operational targets.
5. Maintenance of Infrastructure
We also reviewed the repair and maintenance needs for buildings and transmission lines. Proper maintenance is essential for reliability and long-term asset health.
6. Better Asset Management
Before concluding, the Chief Manager stressed the importance of organizing asset codes, locations, and bay numbers. A well-structured asset database will help us work more efficiently across all units.
Moving Forward Together
The meeting was productive, insightful, and a great reminder that teamwork and communication are key to achieving excellence. With clear priorities and coordinated efforts, we look forward to a more efficient and safer year ahead.
On 01 December 2025, the Morning Shift operators, together with the Maintenance team (led by Mr. Dhan Bir Rai), successfully carried out the replacement of the Silica Gel in the 200 MVA ICT breather system. The existing silica gel had completely turned pink, indicating that it had reached its moisture-absorption capacity and required immediate replacement to maintain the health of the transformer.
Technical Background: Importance and Function of Silica Gel in Transformers
Silica gel is an essential component in the transformer breather assembly. Its primary function is to absorb moisture from the atmospheric air that enters the conservator tank during transformer breathing. When the transformer cools down, it inhales outside air; without a moisture filter, this humid air can lead to:
Deterioration of transformer oil quality
Reduced dielectric strength
Formation of sludge
Accelerated ageing of insulation materials
To prevent these issues, silica gel crystals are used. They are usually blue (or orange) when dry and turn pink as they absorb moisture. The color change is a visual indicator that the gel has reached saturation and needs replacement or regeneration.
Work Carried Out
The team performed the following steps:
Isolated the breather assembly from the 200 MVA ICT.
Removed the saturated pink silica gel, ensuring no contamination entered the breather.
Installed newly purchased silica gel, fully activated and dry.
Reassembled the breather unit and verified proper sealing and airflow.
Result: The replacement ensures that the transformer continues to inhale clean, dry air, thereby protecting the insulation system and prolonging the life of the 200 MVA ICT.
On 29th November 2025, we celebrated a heartfelt farewell for the Rangjung Technical Training Institute students after the successful completion of their three-month internship program at Malbase Substation. As a united team, the members of Malbase Substation came together to organize this farewell as a small token of appreciation, togetherness, and joy.
We are grateful for the dedication and hard work shown by the trainees throughout their internship. The entire team wishes each of them a bright and successful future, and we hope to see them grow into skilled professionals in the years ahead.
Enhancing Substation Reliability: Engineers Review New System Configuration
The substation head, along with a team of engineers, recently conducted a detailed review of the new system configuration to enhance power reliability and ensure uninterrupted electricity supply. By evaluating the electrical topology and network interactions, the team is working to implement a configuration that guarantees continuous, reliable power under all operational conditions. This initiative highlights the substation’s commitment to a resilient and efficient energy distribution system.
Photo Credit @ Mrs. Yeshi Choden | 26-11-2025 | @11:22 Hours
How the 200 MVA ICT Was Brought Back into Service Without Interrupting the 300 MVA ICT under Tala line Shutdown on 26.11.2025
In the 400 kV switchyard, where a one-and-a-half breaker scheme is adopted, we were able to restore the 200 MVA ICT without affecting the supply through the 300 MVA ICT. To maintain continuity, both the 404 Main Breaker (Tala line) and the 405 Tie Breaker were kept closed, while the Tala Line Isolator (404-89L) remained open. With this configuration, 400 kV Bus–I remained energized through the Tala line bay, which in turn continued to feed the 300 MVA ICT and also kept Bus–II energized via the tie breaker. For charging the 200 MVA ICT, it was necessary to close the 409 main bay isolators (409-89M R/Y/B). To do this without causing any interruption, we first opened Breakers 408-52 and 409-52. This operation did not disturb the bus conditions because both Bus–I and Bus–II remained energized via the one-and-a-half breaker configuration. After the area was made safe, all three phases of the 409-89M (R/Y/B) isolators were closed. Once the isolators were secured, Breakers 408-52 and 409-52 were re-closed, thereby charging the 200 MVA ICT on the HV side. Following this sequence, the 200 MVA ICT was successfully energized at 12:07 hours, and subsequently brought on load at 13:01 hours, all accomplished without any interruption to the 300 MVA ICT.
Photo Credit @ Mr. Sonam Dorji |25-11-2025 | @ 11:12 Hours
The 50/63 MVA power transformer, which underwent extensive repair and maintenance at Kolkata, India, was transported back to the substation on 22 November 2025. After completing all logistical arrangements and site preparations, the transformer was safely unloaded and positioned near the 220 kV switchyard on 25 November 2025.
The unloading operation was carried out using specialized heavy-lifting equipment, ensuring structural integrity and adherence to substation safety protocols. This marks a critical step in preparing the transformer for installation, testing, and commissioning as part of the substation’s high-voltage infrastructure.
Photo Credit @ Mr. Kinley Tshering |22-11-2025 | @ 18:12 Hours
The 50/63 MVA transformer has successfully arrived at Balujhora Junction, Pasakha, following all required testing and maintenance procedures. This transformer will soon be commissioned to support the upcoming construction of two new 66 kV transmission lines from Malbase to the Pasakha Industrial Estate. Once energized, it will play a crucial role in strengthening the power supply infrastructure for future industrial development in the region.
Photo Credit @ Mrs. Yeshi Choden | 19-11-2025 | @15:37 Hours
The maintenance team at Malbase Substation is currently carrying out the assembly and fitting of cooling fans for the spare 200 MVA Interconnecting Transformer (ICT). This activity is part of the ongoing effort to restore the spare transformer and bring it back into operational service. To facilitate this work, a shutdown for the 200 MVA ICT has been availed, and maintenance and testing procedures are in full progress. The team is thoroughly inspecting the transformer components, verifying cooling systems, and ensuring that all auxiliary equipment meets the required operational standards. The picture shows the installation of the transformer’s cooling system—an essential component that supports safe loading and efficient heat dissipation during operation. Once completed, the spare transformer will enhance system reliability and strengthen power supply stability for the region.
Photo Credit@ Mr. Sonam Dorji |21-06-2025| @11:36 Hours
In June 2025, our 400/220/66/11 kV Interconnecting Substation at Malbase, TOMS P/ling, had the opportunity to host a group of third-year Electrical Engineering students from the College of Science and Technology. Their internship program was conducted from 16th June 2025 to 27th June 2025, as part of their academic requirement for the Bachelor’s Degree in Electrical Engineering.
Photo Credit @ Mr. Sonam Dorji | 2025 |
The Transmission Control Centre (TCC) team from Thimphu conducted a technical visit to the Malbase Substation to analyze recent power system tripping incidents. The objective of the visit was to study the nature of the disturbances, identify the root causes, and ensure the reliability of the transmission network.
During the assessment, the team carried out a thorough review of disturbance records, relay operations, and system performance logs. To gain a complete understanding of the event, the engineers also proceeded to the switchyard for further on-site inspection. This included checking equipment conditions, verifying breaker operations, inspecting protection schemes, and ensuring that all components were functioning within safe and normal operating limits.
The visit provided valuable insights into the tripping fault sequences and helped the team verify that protective devices at the substation operated as designed. Such field assessments are crucial for maintaining the stability, safety, and continuity of Bhutan’s power transmission system.