Safety and Resources Update
Paving Project Update – Monday, July 6
The paving project is just about complete. There are just a few final details to tend to. The complete lot will be open and available to traffic on Monday, July 6 2026.
__________________________________________________________________________________________________________________________________________
Paving Project Update – Monday, June 29
The High School/Middle School North Side parking lot has been paved and will be open to traffic on Monday, June 29. At that time, all campus traffic will enter and exit through the North Green Beaver Entrance.
Please note that the South Side (Elementary) parking lot, including both the inner and outer loops, will be closed for milling and paving operations. All staff and visitors should park on the north side of the K-12 Complex in the High School/Middle School parking lot.
Please use caution when walking between the north and south sides of the K-12 Complex, as construction activity will continue throughout the area.
The Route 46 entrance will remain closed until further notice.
Please continue to follow all posted signs, barricades, and directions from construction personnel as work progresses. We appreciate your patience and cooperation as we complete this project.
_________________________________________________________________________________________
Beginning tomorrow, June 26, 2026, paving operations will start on the North, West, and East sides of the campus (identified in blue on the map as the North Side Asphalt area).
Current traffic patterns will remain in effect throughout the weekend.
The goal is to have the High School/Middle School North Side parking lot paved and reopened to traffic by June 29, 2026. At that time, all campus traffic will enter through the North Green Beaver Entrance.
Once the North Side parking lot is reopened, the South Side parking area will be closed for milling operations.
Please continue to follow all posted signs, barricades, and directions from construction personnel as work progresses. We appreciate your patience and cooperation during this project.
_____________________________________________________________________________________________
The asphalt replacement project is scheduled to begin on Monday, June 22. It is imperative that all staff, students, and visitors follow posted signs and respect all barricades throughout the duration of the project.
Do not leave campus if your vehicle is parked in the lot, as you may be asked to move it during construction operations.
The State Route 46 entrance will be closed and reserved exclusively for construction vehicles.
Please use the South Green Beaver entrance, indicated in orange on the map below, to access campus.
Once milling operations are completed on the north side of the parking lot, the contractor will immediately transition to the south side to begin grinding operations.
During this phase, the Route 46 entrance will remain closed. Please use the North Green Beaver entrance to access the K–12 parking lot.
The current project schedule calls for all asphalt work to be completed within one week of the June 22 start date, weather and site conditions permitting.
Please use caution when traveling through the area and follow all posted signs and barricades to help ensure the safety of staff, students, visitors, and contractors. We appreciate your patience and cooperation as we complete these important improvements to our campus infrastructure.
As an alternative, parking is available on the stadium side of the street for those who wish to avoid construction-related traffic and parking challenges.