Police Station

Post date: Dec 22, 2017 2:57:30 PM

The project team for the Police Station design had a marathon session on 1/18 working through site issues, room layout and function and specifications for each room. Things are moving very well and it appears that we are still on track to meet the aggressive timetable I've proposed. I'm very pleased with the progress so far and the input of both the architect and the owner's project manager.

We've had a rundown of all building systems operation from Turner House's manager, in preparation for taking ownership of the property.

The attorneys are working through paperwork associated with closing and we should be on track to close on the property by the end of the month.