Bike Path Update

Post date: Dec 20, 2017 8:11:41 PM

Tim, Andrew and I were part of a meeting in North Adams on 12/20 with all of the major parties involved in the Bike Path. The catalyst was to bring new Mayor Bernard up to speed.

The Williamstown portion continues to be in design effort based on comments from the 25% design review. The aspiration is that the North Adams section catches up so that they can reach the 25% design milestone in January-February, with the related public hearing in May.

The attached schedule shows DOT's latest projection - this assumes a combined project going out to bid in Feb 2019 with construction by summer 2019.

We have received and recorded the deed to the donated land that was accepted at Town Meeting in November for the corridor to support the North Adams segment to the airport.