Las Juntas Elementary 

Campus Replacement Project

PROJECT UPDATES:

November 15, 2022
Las Juntas Elementary School is complete. The Notice of Completion was approved at the November 14, 2022 Board meeting.

May 2, 2022

Students and staff moved into the new school building mid-February 2022.  The students were able to finish the second half of the school year in their brand new classrooms.  The old school classroom buildings have been demolished and the grounds and play yard  are in the works.

February 22, 2021

The project is moving along well. More walls have gone up and the building is really beginning to take shape.

February 3, 2021

C. Overaa & Company has erected the first wall on the new school building. School staff are excitedly watching the construction  progress. (See video above)

October 19 , 2020

Site Prep has officially begun this week! (See video below)

1st Demo 2020.10.22.MOV

PROJECT DESCRIPTION:

In the course of the Master Facilities Plan process, all District facilities were evaluated and recommendations were presented in the full report which can be found on the MUSD website. John Muir Elementary was identified as the first project and the school with the greatest need of replacement. Once the John Muir Elementary project was underway the MUSD Bond Team began meeting with advisory groups from the other three elementary schools. Through the process of these advisory group meetings, Las Juntas Elementary was identified as the second project to begin under the Measure R bond program.