Alhambra - Lower Parking Lot Expansion

PROJECT UPDATES:

September 24, 2018

Notice of Completion has been accepted by the Board of Education.

August 20, 2018

Project has been completed well before the first day of school.

June 25, 2018

Work has begun and the project is expected to be completed prior to the start of the 2018-19 school year.

May 2018

Advertised bids were due and Contractor for the project was selected.

In order to improve the school grounds and accommodate student drivers the Board approved the project to expand the lower parking lot by 30 spaces. The project will renovate an underutilized grass area at the front of the campus. In addition the outdated wiring for the marquee will be relocated and updated.

  • Approved by Board of Education: February 2017

  • Contractors:

    • Northern Pacific Corporation

    • American Asphalt Repair & Resurfacing Company, Inc.

  • Project Manager: Jon Novero, RGM & Associates

  • Project Budget: $380,000

  • Project Cost: $376,921

  • Associated Bond Language:

    • "Improve and rehabilitate school grounds, including replacing play structures, athletic facilities, replacing and renovating exteriors, replacing and renovating marquees, and improving walkways."

    • "Improve campus infrastructure, including asbestos abatement, fire alarm systems, weatherizing windows, replacing outdated wiring, replacing leaky roofs."