Fiscal Manager: Adrian Ponce-Rojas
Starting Budget:
Machine Shop Expenses (Fixed): $500
Materials Expenses: $250
Total: $750
Addition to M.E. Acct. (2.6.15): $100
Addition to M.E. Acct. (2.20.15): $100
New Total: $950
Updates:
As of January 9, 2015, the M.E Acct. Stands at $250.
As of January 16, 2015, the M.E. Acct. Stands at $250.
As of January 23, 2015, the M.E. Acct. Stands at $182.71.
As of January 30, 2015, the M.E. Acct. Stands at $98.84
On February 6, 2015, Dr. Frank allowed addition of $100 to the M.E. Acct.
As of February 6, 2015, the M.E. Acct. Stands at $206.95.
As of February 13, 2015, the M.E. Acct. Stands at $67.84
On February 20, 2015, Dr. Frank allowed addition of $100 to the M.E. Acct.
As of February 20, 2015, the M.E. Acct. Stands at $89.27
As of February 27, 2015, the M.E. Acct. Stands at $21.21
As of March 6, 2015, the M.E. Acct. is in the red by $47.30
As of March 13, 2015, the M.E. Acct. is in the red by $47.30
Refer to Final Transaction Report, seen below, for detailed description of all expenses associated with this project.