156B Week 1
Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Leaving designing phase, entering testing phase.
Accomplishments from Previous Week
Finalized dimensions of structure.
Purchased fasteners for testing.
Placed order for Stinger Board in order to begin construction.
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Explore tools for feasible cutting of Stinger Board.
Contact LaserCamm company for safety regarding cutting of Stinger Board.
Finalize deployment decision.
Finalize fastener decision.
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments
Questions regarding dimensions of the support structure of the Statue of Liberty.
Contacted Library of Congress
Exploration of deployment methods.
Exploration of fasteners.
Purchased potential fasteners for testing.
Investigating adhesive properties of Stinger Board
Scotch Weld
2-part Epoxy
Hardware
Instructor Comments from Last Meeting and Actions Taken to Address these Comments
See Risk Reduction Responses to comments.
Risks and Areas of Concern
Adhering fasteners to Stinger Board
Weight of stinger board.
Deployment methods.
Resources or Information Required but not Available
Dimensions of the Statue of Liberty support structure (9/11 Attack = Proprietary information).
Availability of Stinger Board for testing.
Schedule
Describe upcoming milestone
Testing of fasteners
Testing of deployment methods
Purchasing of Stinger Board
3-D modeling with newly determined dimensions
Update Gantt chart.
Budget (list amount spent and amount remaining)
Approximately $50 for testing and brainstorming
Progress on Report and Webpage
Ongoing - Week 1 Project Management has been uploaded.