Overview of Status of Analysis, Design, Fabrication, Tests, etc.
fabrication/assembly
testing
design review from sponsor
Accomplishments from Previous Week
reprint parts adjusted with clearance on medium resolution printer
requested quotes from machine shops
Goals for Next Week (list names after each item). Use specific and measurable objectives.
prepare for Proof of Concept presentation - all members
redesign necessary parts based on feedback from sponsor - all members
create 2D drawings of individual parts to get more accurate quotes and provide detailed instructions to machinists. - all members
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
meeting with sponsor to show parts after class for feedback
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
increase clearance and reprint with medium resolution printer or reprint with high resolution printer
go to sponsor with fully functional part
find a machine shop that machines delrin and get quote for comparison to 3D printed part (cost of machining much higher than cost of 3D printing)
Risks and Areas of Concern
many degrees of freedom
easier to lose adjustment with delrin since friction is low
location conflicts with rf coil.
Resources or Information Required but not Available
3D printing in Polycarbonate for final design rather than machining Delrin? (little to no info online. Must speak with Isiah Freerksen)
Schedule
meet with Bob and coordinate placement of RF coil - Fri May 1st 12:30pm
meet with sponsor for design review - Fri May 1st 4:30pm
adjust designs based on sponsor feedback
create 2D drawings
Budget (list amount spent and amount remaining)
$323.23 Spent
$6,176.77 Remaining