Section 8.1.14

Heating Supply

Heating systems including boilers and radiators shall be installed in accordance with the design, relevant codes and standards to ensure safe operation.

  • Pipework to boiler installed as per manufacturers instruction within the Benchmark book.

  • Boiler condensing pipe must be connected to internal waste pipe to prevent freezing.

  • Follow template for locations of pipes to assist with clean finish.

  • Working to a template for pipe locations will allow the plasterer to use the same template for drilling boards resulting in clean finish when completed.

  • Ensure appropriate tagging is completed before handing over the property.

  • Where necessary, provide boxing and access to heating motorised zone valves.

  • Use a former to radiator pipes to ensure they are fitted to the correct height and width apart whist making sure they are level.

  • 10mm radiator pipe clipped at 450mm centres with hair felt behind.

  • Radiator pipes return into the room via a socket back box with grommets to ensure containment and a neat finish with the plasterwork.

  • Finishing provided to back box once radiator is installed.

  • Support stool used to hold installed radiator whilst decorating is being carried out.

  • Ensure fitted radiators are symmetrical to its surroundings, such as skirting board, windows etc.

  • Ensure radiator pipe tails are not visible once fitted.