Section 7.2.15

Verge

Weatherproofing shall be provided at abutments, intersections, changes in slopes (valleys) and projections to resist the passage of moisture to the inside of the building.

  • Tiles for the valley must be cut away from the roof to prevent dust from blocking up the pours of the breathable membrane and to avoid damage to the roof.

  • Tiles should be cut neatly to the valley former avoiding the use of small pieces.

  • Use (large) tile and a half where necessary.

  • Valley former should extend a minimum of 50mm across the gutter.

  • Saddles are required to be placed at the top of every valley.

  • Lead or a proprietary product acceptable to the pre-formed GRP valley manufacturer can be used.

  • Proprietary verge clips should be used at gables when required e.g. with ‘Forticrete’ SL8 roof aLead used to form the interface of tiles and valley.

  • Lead apron provided to the extended lower section which is terminated underneath the dry verge of the adjoining roof.

  • A creased edge is provided to the lead at the small verge to guide the rain water into the gutter.

  • The foot of the dry valley must be sealed to prevent vermin entry if it extends wider than 10mm, in conjunction with the dry fix system.

  • Tiles for an open valley must not be cut in-situ. Individual tile should be cut away from the roof and bedded with valley pointed using the same mortar.

  • Small cuts must be secured to the adjacent tile using proprietary clips.

  • Intersection between valleys and roofs must be transferred using a lead soaker.

  • Valleys in slated roofs do not need to be pointed providing vermin entry is prevented.

  • Under cloak should project the gable by 38mm – 50mm when using plain tile or slates.

  • 30mm – 60mm when using interlocking tiles.

  • A minimum of 100mm depth of concrete when compressed with the mortar struck and pointed when green using the same mix.

  • Pointing should be neat without excessive mortar on the tiles or slates.

  • Lead flashing will typically be required to link in with a cavity tray.

  • Lead must be installed into brick course by a minimum of 25mm below the cavity tray.

  • Mortar must be raked out prior to the roofer installing the lead and an abrasive wheel must not be used to prevent damage to the cavity tray.

  • Patination oil must be applied to all lead work.

  • Stepped flashing must be installed into the brick joint below the stepped cavity tray.

  • Where slates, plain tiles and flat interlocking tiles are used, soakers or a secret gutter should be installed.

  • Brick joints can be sealed with an appropriate lead sealant.

  • Masonry chimneys projecting through a roof will sometimes require 2 cavity trays to link in with the apron and box gutter.

  • The apron would be installed below the lower tray, the tray will be formed downwards at the apron and upwards on any elevation which enters the roof space.

  • Stepped flashing is the installed but not linking in with a stepped cavity tray.

  • The box gutter is installed below the upper tray. In this area, all side of the tray would form downwards.

  • Flashing to dummy chimneys will be installed as per the manufacturer’s guidelines.