Section 6.4.8

Concrete Floor Decking

Concrete upper floors including hollow core planks shall be placed in accordance with the design and Robust Detail E-FC-4.

  • Isoedge flanking strips to be place around all perimeters.

  • Isoedge flanking strips need to be of sufficient size to allow for -

  • 50mm overlap with Isorubber matt.

  • Depth of screed/concrete.

  • Underlap with skirting board.

  • Ensure Isoedge flanking strip is continuous around corners.

  • Ensure Isoedge flanking strip is continuous around any SVP boxings.

  • OIsorubber mat should overlap a minimum of 50mm in all locations including with Isoedge flanking strip.

  • Laps must then be sealed with proprietary tape.

  • Attention to detail required around corners.

  • Screed/concrete should never come in to contact with concrete planksnce installed, fully grout with a lean mix concrete.

  • Finish floor screed/concrete as per design and installed in accordance with the manufacturer’s recommendations.

  • Isoedge flanking strip must be trapped between the concrete and the skirting board to prevent the passage of sound.

  • Trim back flanking strip flush with skirting board when installing floor finish.