Section 5.2.1

Suspended Floor Beams

Suspended ground floors hold a critical function within a property. Floor systems designs must be followed at all times. Regular checks on the quality of materials are paramount to its success.

  • Precast concrete beams delivered to site ideally should be installed on the same day.

  • If this is not possible, beams should be stored on prepared ground on skids positioned vertically in alignment and in an area where they will not get damaged.

  • Beams should safely lifted onto the substructure.

  • Beams are required to be placed on a DPC.

  • Manually set out the beams ensuring the minimum required bearing of 90mm is achieved on substructure walls.

  • Use the infill blocks to gauge locations of the beams.

  • Beams set out to avoid pipework rest bends.

  • Pipe positions should be checked after the blocks are placed to ensure they have not moved position.

  • Checks should take place before grouting of the block and beam.