SAVE Bren Mar
from a Data Center
bren mar today - your neighborhood tomorrow
Fairfax Co. leaders discussing zoning, standard changes for data centers amid development pushback
WUSA 9 - Matthew TorresMarch 12, 2024
NBC 4 Washington - Julie Carey
March 12, 2024
April 9, 2024
May 2 Update
The county is actively reviewing changes to the Zoning Ordinance for Data Center to add increased protections for residents. Our community must be vocal and demand that these changes include robust protections for residents from data centers like that proposed at Plaza 500. We believe if the county acts by the July 16 Board of Supervisors meeting these would have to apply to Plaza 500 (and all future data centers in the county).
On May 2, 6, and 7 the county will be holding virtual community meetings on the proposed changes. Use the Take Action Resources to raise the 6 Key Changes we need at the meetings and in emails to the county Department of Planning and Development, the Planning Commission, and the Board of Supervisors.
NOW is our opportunity to influence the draft amendment text!!
Send an email and plan to attend the meetings (info and resources below)
April 15 Update:
On April 9, over 130 residents attended the Dominion Energy Community Meeting/Open House to express their concerns about the proposed data center electrical substation. In the coming months there will be opportunities to engage Dominion Energy, the State Corporation Commission (which reviews the substation application), and the Planning Commission and Board of Supervisors through emails, public hearings, and other communication.
Save Bren Mar is hard at work determining our next steps in terms of engagement and will be in touch very soon!
March 12 Update:
Thank you for taking action to contact the Board of Supervisors! More than 400 emails have been sent to the Board and civic and community associations across the county are joining us! Our efforts are drawing attention from the Board and media. Please keep it up because more is needed.
The Board has committed to moving forward on data center changes to the Zoning Ordinance with a July completion date. While this is a positive development, they must act first and immediately to change the Zoning Ordinance to require a Special Exception for data centers in all Industrial Districts. This is the only way to ensure a public process and approval by the Board of Supervisors.
We remain convinced that the Board does have time to lawfully adopt a Zoning Ordinance Amendment to end by right development of data centers. While most site plan submissions are typically approved within "60 days from receipt of a complete submission" (see Zoning Ordinance § 8100.7), they take on average 6 to 9 months before a determination is made. This likely means the Board has more time than it thinks because "the review period only includes the time the site plan is in for County review and does not include such time as may be required by the applicant for revisions or modifications in response to comments from the County to comply with the Ordinance."
We continue to engage with the county concerning our efforts and are pushing them closer to action. We met with Sup. Jimenez and his staff to express our community concerns and call on him to take action. We are urgently awaiting his response and plan.
Take Action
Send an Email NOW to the Fairfax County Planning Department, Planning Commission and Board of Supervisors Demanding they Pass Data Center Amendments that Protect Residents. Use the template below. We need as many emails as possible to sway them.
Attend the Planning Commission Infrastructure Committee Meeting on May 9 at 8:30pm. The Committee will be discussing the proposed data center zoning amendments. The meeting will be held in Conference Room 11 of the Fairfax County Government Center, 12000 Government Center Pkwy, Fairfax, VA 22035.
Attend and Sign-Up to Speak at the June 5 at 7pm, Planning Commission Public Hearing on Data Center Amendments to the Zoning Ordinance. Location: Board Auditorium, Fairfax County Government Center, 12000 Government Center Pkwy, Fairfax, VA 22035. Speaker Sign-Up (Under Application Name put Data Center Zoning Ordinance)
Attend and Sign-Up to Speak (coming soon) at the July 16, Board of Supervisors Public Hearing on Data Center Amendments to the Zoning Ordinance. Location: Board Auditorium, Fairfax County Government Center, 12000 Government Center Pkwy, Fairfax, VA 22035.
Join our contact list to receive updates. Your information will not be shared.
Share your story about why you live in the community and your concerns about the data center. Show the Board how misplaced heavy industry will impact you and your family.
Spread the word by sharing this website and Call to Action on social media, NextDoor, and all other places that will attract local attention. Continue to build the movement of those involved.
Updated May 2
call to action
Send an Email to the Department of Planning, Planning Commission and the Board of Supervisors NOW
Sample templates below
Sample templates below
Email Department of Planning and Development, Planning Commission, and the Board of Supervisors
Sample Email to Department of Planning and Development, Planning Commission, and Board of Supervisors:
Email (all): data-centers@PublicInput.com; plancom@fairfaxcounty.gov; clerktothebos@fairfaxcounty.gov; mason@fairfaxcounty.gov; chairman@fairfaxcounty.gov; braddock@fairfaxcounty.gov; Dranesville@FairfaxCounty.gov; huntermill@fairfaxcounty.gov; Franconia@fairfaxcounty.gov; mtvernon@fairfaxcounty.gov; providence@fairfaxcounty.gov; springfield@fairfaxcounty.gov; sully@fairfaxcounty.gov; peter.murphyjr@fairfaxcounty.gov; john.ulfelder@fairfaxcounty.gov; timothy.sargeant@fairfaxcounty.gov; alis.wang@fairfaxcounty.gov; mary.cortina@fairfaxcounty.gov; john.carter@fairfaxcounty.gov; chris.landgraf@fairfaxcounty.gov; walter.clarke@fairfaxcounty.gov; jeremy.hancock@fairfaxcounty.gov; evelyn.spain@fairfaxcounty.gov; phillip.niedzielski-eichner@fairfaxcounty.gov; candice.bennett@fairfaxcounty.gov; brenmar@googlegroups.com
Subject: Needed Changes to Data Center Zoning Ordinance Amendment
Text: Dear Department of Planning and Development, Planning Commission, and Board of Supervisors:
As a resident of Fairfax County who is deeply concerned by the impact of data centers on our communities I would first like to thank you for taking action to strengthen data center requirements in our county. I urge you to act without delay and to commit to your timeline of enacting changes at the July 16 Board of Supervisors hearing.
While the county provided draft text is a start in the right direction, I am asking you to make the following edits and additions to the draft text to the Data Centers proposed Zoning Ordinance amendment prior to the Planning Commission public hearing on June 5.
The changes below will ensure that residents across the county will be protected from any harmful impacts of any type of data center, including massive data centers larger than 80,000 sq. ft., and ensure that as Chairman McKay indicated, Fairfax County can have the highest standard in the state and country in terms of protecting residents.
Thank you,
[NAME]
[ADDRESS]
Requested Changes to County Data Center Amendment
Key Asks
All data centers must require a Special Exception, especially in I-5 Districts that place residents at greatest risk for massive data centers. This includes:
All data centers larger than 80,000 sq ft. (massive data centers);
All data centers in I-5 Districts directly adjacent to Residential districts ;
All data centers that have the possibility to exceed a 12 MW electrical load;
Any exception to the requirement that equipment for data centers (HVAC, generators, etc.) be enclosed
The county must set a minimum setback from residential districts of at least 2,640 feet (½ mile) from residents for massive data centers larger than 80,000 sq. ft. or that exceed a 12 MW electrical load;
A Minimum 1 mile distance from metro station entrances must be required
Permissions:
All data centers must require a Special Exception, especially in I-5 Districts that place residents at greatest risk for massive data centers. This includes:
All data centers larger than 80,000 sq ft. (massive data centers)
The county must recognize data centers greater than 80,000 sq. ft. as massive data centers requiring closer scrutiny to ensure conformity with the Comprehensive Plan and mitigate impact on neighboring properties.
All Data Centers in I-5 Districts directly adjacent to Residential districts
The proposed county rationale that data centers should be pushed to I-5 and I-6 districts ignores the reality that nearly all I-5 districts are directly adjacent to Residential districts and raise the very concerns with noise, visuals, and environmental impacts, that these proposed amendments are seeking to address.
All Data Centers that have the possibility to exceed a 12 MW electrical load
No other industry has such high energy demands that also impact surrounding districts, therefore any building or site plan requiring more than 12 MW of electrical load must require Special Exception approval. Current data centers consume 5 to 20 MW for buildings up to 100,000 sq. ft. and 20 to 100+ MW for over 100,000 sq. ft. (the recently approved Chantilly data center anticiaptes 54 to 75 MW). With the move towards AI, energy usage of data centers will continue to grow exponentially, which means more noise and greater impact on surrounding districts. An article from The Next Platform highlights this impact: “The power consumption goes from 500 watts to 700 watts for a general enterprise-class server to between 2,500 watts and 4,500 watts for a single AI training node. Imagine the heat generated from that compute horsepower then visualize an air conditioning unit trying to cool it with mere chilled air.”
Requires the construction of a substation
Use Standards:
Equipment screening/enclosures:
A Special Exception must be required for any exception to the requirement that equipment for data centers be enclosed (HVAC, generators, etc.)
The proposed requirement that all equipment for data centers (HVAC, generators, etc.) is a positive addition. However, the exception where the Director of Land Development Services determines that it is not mechanically feasible must be changed to a Special Exception requirement. Noise and other factors caused by exterior equipment are the biggest concerns for residents and decisions of this magnitude should rest solely with the Planning Commission and Board of Supervisors. Past approvals of massive data centers have shown the only way for the county to obtain the necessary proffers to protect residents, specifically around noise, has been through the Special Exception process.
Equipment enclosures will grow more and more mechanically challenging as data center technology advances and requires more cooling As such, the county should not provide administrative exceptions to the issues that will have the biggest impacts on residents, especially given the need for data centers to locate close to substations or need new substations built, that many land parcels for data centers are directly adjacent to or within ½ mile of residentially zoned districts, and the trend of data centers moving towards AI servers that require five times more power and much more cooling,
If an exception is needed, it should go through the Special Exception process. If the data center developer is unable to comply with the equipment screening/enclosure standards they must come before the Planning Commission and Board of Supervisors and explain why and what they will do to negate the impact on their surrounding districts.
Size thresholds for by-right data centers:
As indicated under the Permissions section, the county must require all data centers greater than 80,000 sq. ft. (massive data centers); be approved by Special Exception, regardless of district. I-5 Districts are immediately adjacent to residential districts.
The proposed county rationale that data centers should be pushed to I-5 and I-6 districts ignores the reality that all or nearly all I-5 districts are directly adjacent to residential districts and raise the very concerns that these proposed amendments are seeking to address.
A Special Exception should be required for data centers that have the possibility to exceed a 12 MW electrical load;
The more electricity that is needed, the more HVACs and generators are needed, adding to the impacts on noise and other factors. If a data center requires over 12 MW or requires a substation to be built, or if other data centers already exist within ¼ mile, then they should go through a Special Exception.
For example, if a data center requires 75 MW, and 3 MW backup generators are used, then it will need 25 generators and enough HVACs to cool (see Chantilly Premier RZ 2022-SU-00019 noise study requiring over 130 rooftop fans for its 75MW data center). These excessive power requirements are also straining the grid and hampering efforts to combat climate change.
Setback from residential:
The county must set a minimum setback from residential districts of at least 2,640 feet (½ mile) from residents for data centers >80,000 sq. ft (massive data centers) or that have the possibility to exceed a 12 MW electrical load that creates additional noise, visual. and other environmental impacts.
This is generally consistent with previously approved data centers in the county (see RZ 2022-SU-00019), with a set-back of 0.4 miles and the recommendations of the HOA Roundtable of Northern Virginia. County comparisons to the minimum distance to barns, extraction, or crematory is not a similar comparison as those don't run 24/7. Additionally, barns and extraction facilities are a different nature of use not typically found in urbanized areas of the county. Similarly, a crematory's impact on neighboring property is of a different nature than a data center (i.e., data center noise propagates farther and differently than emissions from a crematory).
Comparisons to Loudon County fail to include the fact that Loudon is also proposing to eliminate by-right data centers in most locations, and have additional requirements related to change in building height, and building step-back. The county must not cherry pick comparisons.
Data Centers less than 80,000 sq. ft. or that are less than 12 MW electrical load must be setback at least 500 feet and fully eliminate any impact to residents, including noise, and other environmental impacts.
Distance to residents could be based on a scale with size or ability to enclose noise sources. The county could encourage small data centers that adhere with all other requirements suggested and that have no impact on neighboring properties to move their high tech, high salary jobs into locations that also permit ground level store fronts, provide nearby residential options, metro access, etc.
Distance from metro:
A Minimum 1 mile distance from metro station entrance must be required.
A minimum distance from a metro station is a welcome addition that recognizes the unique nature of these sites with high-population and employment centers near transit. This distance must be expanded to 1 mile and rather than relying on a SE, the distance from the metro should be permitted or not permitted based on size and enclosure, with mixed use requirements required. This would prohibit massive data centers in a metro area that would be the relative job killer. The county should encourage smaller DCs with no impact on neighboring properties to move their high tech, high salary jobs into locations that also permit ground level store fronts, provide nearby residential options, etc. The county must discourage massive data centers and encourage development that replaces losses in office buildings, etc.
Noise Study:
Use Standards must me strengthened, as indicated above, for Noise Study to have impact
While a noise study requirement is welcome, including post-construction. This requirement does not go far enough to address impacts on residents. The above use standards must be strengthened in order for the impact of noise to be eliminated.
The cumulative impacts of noise should be examined when approving multiple data center buildings on a site or when other data centers already exist within 1000 feet.
The noise study performed for the Chantilly Premier data center which was modeled on upgraded noise mitigation measures, demonstrates that in order for noise to be below the nighttime standard of 55 dBA, the range is out to about 1000 feet, which is why a greater setback for residential is needed, especially for massive data centers (larger than 80,000 sq. ft). Given that the dB(A) scale is not an accurate measure of the noise, the County should consider a greater distance.
Building Design:
Requirements for building design are a welcome addition.Additionally, the recommendations from the Northern Virginia HOA Roundtable, concerning building design should be considered where not already recommended in the amendment:
“Data centers can have significant adverse visual impacts. They should be sited and designed to avoid these, especially for viewsheds that are valued by the community, including historic and cultural resources, residences and neighborhoods, parks and schools, and natural resources such as forested areas.
Data center architectural design should be aesthetically compatible with adjacent uses, particularly residential neighborhoods, parks and schools. Exteriors should use fenestration, windows, variation in exterior materials, and other features to avoid monolithic appearances and to be congruent with the adjacent uses that have a view of the data center. Data centers should incorporate landscaping that is similar and compatible with that of the surrounding uses. Fencing and accessory structures and features (guard stations, waste areas, accessory equipment, parking areas, etc.) should also be designed and landscaped to be aesthetically compatible with the surrounding land uses.”
Additional Recommendations
Environmental Concerns:
Given the tendency for data centers buildings to cluster together, Tier IV diesel generators should be required if green alternatives are not being used (e.g. microturbines, or hydrotreated vegetable oil (HVO))
Call Board of Supervisors
Phone Numbers
Chairman Jeff McKay: 703-324-2321
Vice Chair Kathy Smith (Sully) : 703-814-7100
Andres Jimenez (Mason): 703-256-7717
James Walkinshaw (Braddock): 703-425-9300
James Bierman (Dranesville): 703-356-0551
Walter Alcorn (Hunter Mill): 703-478-0283
Rodney Lusk (Lee): 703-971-6262
Daniel Storck (Mount Vernon): 703-780-7518
Dalia Palchik (Providence): 703-560-6946
Pat Herrity (Springfield): 703-451-8873
Script
As a resident of Fairfax County who is deeply concerned by the impact of data centers on our communities I would first like to thank you for taking action to strengthen data center requirements in our county.
While the draft text is a start in the right direction, I am asking you to make the following edits and additions to the draft text.
The changes below will ensure that residents across the county will be protected from any harmful impacts of any type of data center, including massive data centers larger than 80,000 sq. ft., and ensure that as Chairman McKay indicated, Fairfax County can have the highest standard in the state and country in terms of protecting residents.
Key Asks
All data centers larger than 80,000 sq. ft. (massive data centers) must be approved through Special Exception;
All Data Centers in I-5 Districts must require a Special Exception;
The county must set a minimum setback from residential districts of at least 2,640 feet (½ mile) from residents for massive data centers larger than 80,000 sq. ft. or that exceed a 12 MW electrical load;
A Special Exception must be required for any exception to the requirement that equipment for data centers (HVAC, generators, etc.) be enclosed;
A Special Exception should be required for data centers that have the possibility to exceed a 12 MW electrical load and that will likely have similar noise impact as massive data centers;
A Minimum 1 mile distance from metro station entrances must be required
This information will be used to demonstrate the vibrant and diverse community that we are a part of and the impact on individuals and families that will occur if a data center is able to go forward without public input or review and approval by the Board of Supervisors.
your supervisor on the record
In January, the Board of Supervisors approved a Chantilly data center through a Special Exception review, stating that the review, which included extensive community input, resulted in plan changes that would meet the County recommended standards.
Plaza 500 will not have such review if by right development is not stopped.
Are the Supervisors' words meaningful if they let the Plaza 500 data center be built without higher standards, Board review, and public input?
Supervisor Quotes
Chairman Jeff McKay
"If we are going to do any data centers in Fairfax County, even if its one-fifth or one-tenth of what other people are going to do, the ones we do in this County are going to be done at the highest standard we can possibly foresee."
"I will also support making sure that this is the standard on any data center that comes into Fairfax County, because frankly we need to be setting the nationwide standard on these. And I believe that we can do that and that’s what we asked for and this application will do that."
"Our job is to do a land use analysis to look at this application and weigh at against what our standards are, question ourselves whether our standards are the highest in the Commonwealth and I would argue probably put them up against most in the nation in dealing with data centers. Are they at that standard? And they are. Does this application meet those standards? It does."
"There are times where commitments are made through the land use process that people think will not be upheld. And that’s why I’m making sure not only we got some things on the record but also making sure that the proffers are so extensive. The proffers are legally binding. They exceed the zoning ordinance standard, The protections for noise for people related to this property are better than the protections for noise anybody else living around industrial properties in Fairfax County unless there’s a proffer like this in here. And most industrial cases don’t have that…There are some elements of the proffer here that most certainly exceed what our own county requirements are for industrial/commercial properties in other parts of the county. And for me that's a bellwether for if we should make this change. Are we doing better than what our own zoning ordinance tells us that we need to be doing? And I think that this application does that."
Vice-Chairman Kathy Smith (Sully District)
"Again, I really appreciate the public participation, that input helped to prompt real improvements to the application."
“At this public hearing, at the Planning Commission hearing, in other community meetings and countless correspondence, we’ve heard concerns about noise, visual impact, energy demand, water quality, and the like. But we’ve also heard how thoroughly this applicant has addressed these concerns by submitting a more robust proffer package than any data center applicant has previously provided in this county.”
Supervisor Andres Jimenez (Mason District)
“I don’t think data centers should be anywhere near communities. I don’t think we’re going to turn Mason into a data center hub. The bigger longer-term picture is what do we do with data centers throughout Fairfax County.” (Source: Annandale Today, Supervisor Jimenez Wants to Make Mason District a Cultural Hub, Jan. 19, 2024.)
Supervisor James Walkinshaw (Braddock District)
"This is an issue that we really as a county have to get right."
"We also have an opportunity to establish standards that are the highest in the Commonwealth if not the highest in the nation and I think the work of this application and the work that staff has done with our data center report put us on that path. I think as we move forward into the future we will be able to put in place standards that are even higher than what we are talking about today and that were in the data center report."
"The challenge is if we can establish the highest standards here and hold data centers to those standards we can do better than other places where they would be build if they were not built here."
"This case meets all of our existing standards and meets all of the higher standards that we are likely to consider in the years to come."
Supervisor James Bierman, Jr. (Dranesville District)
"What message would it send that we’re accepting a data center without stuff from the data center report? But I got news for you, there’s a lot of proffers here, there’s a lot here with this data center that matches this report."
"The report here says you should work on water treatment and consider water treatment before it goes in your watershed. Do we proffer about water treatment? We do. There’s something in here about proffers based on lower noise requirements. We’ve already been over that. We proffered lower noise requirements. There was literally something in here about a post-construction noise study and we’ve got that right here as well."
"We asked and we got a lot out of this applicant to make this a responsible plan."
Supervisor Rodney Lusk (Franconia District)
[Nothing on the record.]
Supervisor Walter Alcorn (Hunter Mill District)
“I’d encourage staff to move quickly on this and, frankly, if there are things that are ready to move before the end of the year [2023], I would suggest that they do that,” Alcorn said. “This is a moving target . . . This technology is changing. The practices are changing, so there may be some things that we would need to do even sooner than the end of the year.” (Source: Gazette Leader, Fairfax leaders aim to stay ahead of curve on data centers, May 12, 2023)
Supervisor Daniel Storck (Mount Vernon District)
"Recognize where data centers should and shouldn’t be. Recognize the ability to put them in industrial centers. I think that’s why we’ve created that opportunity and option. I think even some commercial places it’s appropriate. Obviously where it’s not is areas that are at residential locations."
"I want to support that need [of data centers] but I want to do it in a way that minimizes its impact because every time you do a data center, every time you do a major construction like this there is an impact."
Supervisor Dalia Palchik (Providence District)
[Nothing on the record.]
Supervisor Pat Herrity (Springfield District)
"It comes before the board has been able to discuss and issue our guidance on data centers."
"Springfield garage looms over the neighboring church and as I drive by that thing and look at what we did to that church it bothers me what we’re going to do here and it’s out of character with that area in the county."
Our community
Residential and recreation land surround Plaza 500 on both sides of the Fairfax / Alexandria line.
There should not be a data center this close to our neighborhoods.
Color Key
Yellow (Residential) | Purple (Planned Residential and Commercial) | Green (Recreation and Parks) Blue (Commercial) | Red (Industrial)
What You Need to Know
Out-of-state developer, Starwood Capital Group, submitted a site plan to build a massive 461,444 sq. ft., 70 ft. tall industrial data center in the heart of a residential community. The data center will be less than 260 ft. from residential property, and its new very large electrical substation will be less than 100 ft. away. This would be the 5th largest data center in the County and the closest of its size to residential homes.
There will be no public hearings or public input without emergency action by the Board of Supervisors because this is a by-right "Permitted" development. We agree with the County staff recommendation to revise permissions to require Special Exception approval for data centers, regardless of size.
The submitted site plan calls for a massive industrial data center and new electrical substation at the site of Plaza 500's current offices and warehouse. Starwood Capital Group will use by-right "Permitted" development under the Zoning Ordinance to demolish the site and build the data center without public input or negotiation with the County.
This data center would be in the heart of our residential community -- less than 260 ft. from residential property, and the new very large electrical substation will be less than 100 ft. away. It will have a negative impact on our community: creating noise and light disturbance 24 hours a day 7 days a week, requiring very high energy and water use, emitting potentially harmful pollutants, and impacting property values.
This massive data center site plan will drastically change the community and cut off access to future mixed use development (PDF). Our community anticipates positive residential and retail development over the coming years with the redevelopment of Landmark Mall and Van Dorn Street. A data center would be a permanent eyesore among other residential developments, amenities, and positive growth.
What is it? Data centers are industrial complexes that house acres of computer systems for storing virtual information. Massive infrastructure must be built to support these complexes, including transmission, water, and sewer lines. Data centers are slated to account for a fifth of the world's electricity usage and more than 3% of carbon emissions by 2025. In 2020, data centers consumed an estimated 174 billion gallons of water. A 15-megawatt data center can use up to 360,000 gallons of water a day.
National Parks Conservation Association, Keep Massive Industrial Data Centers Away from our National Parks
References
Site Plan
Plaza 500 Site Plan (138.4MB PDF) (Feb. 5, 2024) and Fairfax PLUS Record SP-2024-00003
Fairfax County's Plaza 500 PLUS Records, General Parcel Report, Environmental Parcel Report, Tax Assessment Report
Electrical Substation
Plaza 500 News
WUSA9: Concerns grow from those who live near proposed data center in Alexandria (Apr. 9, 2024)
Annandale Today: Residents concerned about Dominion’s substation project (Apr. 10, 2024)
Patch (Reston, Va): Data Center Zoning Policy To Be Updated By Fairfax County Board (Mar. 12, 2024)
WUSA 9: Fairfax Co. leaders discussing zoning, standard changes for data centers amid development pushback (Mar. 12, 2024)
NBC 4 Washington: Residents ask Fairfax County to require public input about data centers (Mar. 12, 2024)
ABC 7 WJLA: Fairfax County considers enhancing data center guidelines (Mar. 12, 2024)
Fairfax County Times: Homeowners Associations implore Board to require public input for data centers (Mar. 8, 2024)
Data Center Dynamics: Starwood re-proposes data center in Alexandria, Virginia (Mar. 1, 2024)
Annandale Today: Bren Mar Park residents urge the BoS to act against a by-right data center (Feb. 27, 2024)
WTOP: Northern Virginia neighbors concerned over planned data center that’s more than 100 feet tall (Jan. 24, 2024)
Annandale Today: Supervisor Jimenez Wants to Make Mason District a Cultural Hub (Jan. 19, 2024)
Alexandria Now: Alexandria's Smoot Lumber Yard Closing Today After 200 Years in Business (Dec. 1, 2023)
Previous Success
Data Center Dynamics: Fairfax Residents Block Suspected Data Center in Alexandria, Virginia (Nov. 18, 2022)
Data Center Knowledge: Fairfax County Residents Push Back on Data Center Zoning (Nov. 17, 2022)
FOX 5 Washington DC: Fairfax County Residents Organize Against Data Center Rezoning (Nov. 16, 2022)
Data Center Dynamics: Residents Protest Suspected Data Center Plan in Alexandria, Virginia (Nov. 16, 2022)
Alexandria Living Magazine: Bren Mar Residents Concerned About Data Center Possibility (Nov. 15, 2022)
Annandale Today: Residents Oppose Industrial Rezoning (Oct. 29, 2022)
County Recommendations
Fairfax County Data Centers Report and Recommendations (Jan. 9, 2024)
Fairfax County Environmental Quality Advisory Council Recommendations for Siting of Data Centers (PDF) (June 14, 2023) and Follow-up on Data Center Siting (PDF) (Nov. 21, 2023)
Community Letters to County and Public Testimony
Public Comment Testimony and Chairman McKay Response (Feb. 20, 2024) (Video)
Community Letter 6 (Feb. 19, 2024)
Community Letter 5 (Jan. 19, 2024)
Community Letter 4 (zMOD) (May 2, 2023)
Community Letter 3 (Nov. 16, 2022)
Bren Pointe Community Letter 2 (November 10, 2022)
Bren Pointe Community Letter 1 (October 26, 2022)
Data Center Concerns
Business Insider: Virginia's 'Data Center Alley' residents say an eerie hum is keeping them up at night (Nov. 27, 2023)
FFXnow: Fairfax County considers size, noise and environmental guidelines for data centers (Oct. 19, 2023)
WUSA9: What's all the data center noise about? (Apr. 7, 2023)
Prince William Times: Fairfax County staff asks Prince William officials to rethink data center plan (Mar. 10, 2022)
Baxtel: Noise pollution from Prince William data center riles locals (July 22, 2022)
Fauquier Times: Manassas neighborhood battles noise from data centers (Aug. 24, 2022) (600 feet from homes; Bren Mar neighbors would be less than 300 feet from building)
Data Center Frontier: Loudoun County Passes New Rules to Limit Data Center Growth (Oct. 5, 2022)
Q&A
What is in the site plan?
We know the square footage, height, and placement of two data center buildings on the property, as well as the placement of a new electrical substation. The site plan shows the data center buildings are less than 260 feet away from residential property to the West and 570 feet away from residential property to the North. The electrical substation will be less than 100 feet away from residential property.
The site plan does not have all the details needed to fully understand the impact of the data center. For example, there are no details on the type, size, or location of cooling towers, emergency backup generators, fuel storage, or electrical transmission lines.
Why is action needed immediately?
We understand the County is required to "accept" the site plan 60 days after submission. County staff have said that the Board of Supervisors has until acceptance of the site plan to change the Zoning Ordinance standards that would apply to the site. An urgent amendment to the Zoning Ordinance to change the by-right “Permitted” development of data centers to a “Special Exception” before acceptance is the only way ensure a public process for hearings, reviews, and changes to protect residents. Both the Board of Supervisors and Planning Commission will need to provide public notice and hearings on the Zoning Ordinance amendment. The time is tight, but it's possible and not without precedent.
What did County staff recommend about by right data center development?
In their Data Centers Report and Recommendations, County staff recommended the Board of Supervisors "consider revising permissions to require SE approval for data centers, regardless of size, in the C-3, C-4, and I-2 through I-6 Districts. In addition to recommendations ... under other topic areas, standards for special exception review should include the consideration of the size of a proposed data center and its distance (buildings and generators) from surrounding existing and planned residential development."
Are Fairfax County standards the highest in Virginia?
Not yet. There are no data center-specific standards that apply to data centers built in an I-5 District. The Board of Supervisors will hopefully consider higher standards, including those proposed in recent County Recommendations, but any higher standard will not apply to Plaza 500 if by-right "Permitted" development is allowed to continue.
How is the Plaza 500 data center different than the Chantilly data center approved in January?
The Chantilly data center will be 110 ft. tall. It will have smaller square footage than Plaza 500 and will be nearly half a mile away from residential property.
This website relies on data centers. Why oppose them?
Data centers are important for modern, internet-enabled living. Mega data centers should be located near similar heavy industry and away from residential homes because of the impact they have on neighboring properties.
Who is organizing the Save Bren Mar effort?
Local concerned private residents. We are not affiliated with any group, organization, or company. Contact us at SaveBrenMar@gmail.com to get involved.
Together we can
SAVE our communities!
SAVE our communities!