Provision of Phase 1 Site Preparation Work for The Proposed Refinery and Petrochemical Integrated Development (RAPID) Project At Pengerang Johor - Package 2.
Client: Petroliam Nasional Berhad
Approximate Construction Cost: RM 509,000,000.00
Commencement Date: 15 December 2012
Completion Date: 31 December 2013
Provision of Phase 2 Site Preparation Work for The Proposed Refinery and Petrochemical Integrated Development (RAPID) Project - Package 18D
Client: Petroliam Nasional Berhad
Approximate Construction Cost: RM 766,000,000.00
Commencement Date: 1 July 2014
Completion Date: 31 December 2015
Procurement, Construction and Commissioning (PCC) of civil and infrastructure works at off-plots area for the utilities, interconnecting and offsite (UIO) facilities for rapid project (Package 14-0403)
Client: OUI JV
Approximate Construction Cost: RM 180,600,440.61
Commencement Date: 24 May 2016
Completion Date: 24 October 2018
Utilities, Interconnecting Offsite (UIO) facilities Construction and Commissioning (CC) of marine works for Storm Water Outfall (SWO) and Effluent Treatment Plant (ETP) outlet pipeline for rapid project (Package 14-0500).
Client: See Yong & Son Construction Sdn Bhd
Approximate Construction Cost: RM 108,872,812.00
Commencement Date: 1 July 2016
Completion Date: 1 September 2017
Proposed development of New LCC Terminal and associated works at Kuala Lumpur International Airport, Sepang, Selangor. Works package EW01A. Earthworks to privatization packages areas.
Client: Malaysia Airport Holdings Berhad (MAHB)
Approximate Construction Cost: RM 80,000,000.00
Commencement Date: 14 May 2010
Completion Date: 13 December 2010
Construction and completion of earthworks and main drainage systems for Universiti Industri Selangor (UNISEL) Main Campus, Mk Batang Berjuntai, Selangor Darul Ehsan
Client: Talam Builders Sdn Bhd
Approximate Construction Cost: RM 71,566,534.24
Commencement Date: 1 July 2001
Completion Date: 31 May 2002
Site Setting, Development, Levelling & Preparation For Ulsado Project Petron, Port Dickson Refinery
Client : Petron Malaysia Refining & Marketing Bhd
Construction Cost: RM 2,700,000.00
Commencement Date: 11 February 2019
Completion Date: 31 November 2019
Earthwork Package For Marine Import Facilities 2 Project Petron Port Dickson Refinery, Fwecm Project No: EC1280A4, Enquiry
Client : Petron Malaysia Refining & Marketing Bhd
Construction Cost: RM 8,300,000.00
Commencement Date: 1 October 2018
Completion Date: 28 February 2020