Client: Town of Beaufort
Engineering Partner: Rivers Engineering
Construction Partner: T. A. Loving Company
Delivery Method: Design-Bid-Build
T. A. LOVING COMPANY
CONTRACT 1 - WASTEWATER COLLECTION SYSTEM REHABILITATION
The work to be performed under this contract consists of rehabilitation of portions of the existing wastewater collection system. The project consists of constructing approximately 45-point repairs, lining 9,200 LF of 8"-12" existing gravity sewer, 4,498 LF of 8" and 12" gravity sewer main, replacing 45 manholes, and replacing 216 sewer services.
SUNLAND
CONTRACT 2 - WATER DISTRIBUTION SYSTEM IMPROVEMENTS
The work to be performed under this contract consists of replacement of portions of the existing water distribution system in the Town of Beaufort, North Carolina. The project consists of constructing approximately 16,500 LF of 6" water mains, approximately 3,400 LF of 8" water mains, approximately 3,800 LF of 12" water mains, 92 - 6" gate valves, 14 - 8" gate valves, 10 - 12" gate valves, replacement of 36 fire hydrants, installation of 2 new hydrants, replacement of 370 water service connections, abandonment of approximately 20,000 LF of existing water mains using flowable fill, and abandonment of existing 2" water mains by capping, and related work.
SUNLAND
CONTRACT 3 - STORMWATER DRAINAGE SYSTEM IMPROVEMENTS
The work to be performed under this contract consists of stormwater drainage system improvements for six (6) areas within the Town. The project consists of constructing approximately 5,800 LF of 15" to 36" stormwater pipe, 82 related drainage structures and removing or abandoning existing pipe.
T. A. LOVING COMPANY
Project Manager
Sean Owens
Project Superintendent
Antonio Sutton
Assistant Superintendent
Thom Schulte
Updated (2/20/2025):
T. A. LOVING COMPANY
CONTRACT 1:
Sewer improvements completed on Ronnie Rd.
Sewer improvements completed on Craven Ave.
Sewer point repairs and replacement completed on Campen Rd. Sewer lining scheduled to be completed in February followed by sewer service replacement in early March.
Sewer point repairs completed on Ann St. near Beaufort Inn. Sewer lining scheduled for late February, followed by sewer service replacement.
Sewer improvements completed on 2/3 of Chestnut Dr.
Remaining sewer work (point repairs, replacement, and lining) on Chestnut Dr. scheduled for March and April 2025
New sewer installation completed on Sunshine Ct. Point repairs, sewer lining and service replacement work remains. Point repairs are scheduled for late March of 2025 followed by sewer lining and service replacement.
Sewer point repairs started on Cedar St. Additional point repairs are required prior to sewer lining and are scheduled to be completed in March. Sewer lining in late April.
Sewer Point Repairs completed on portions of Front St. near Live Oak. Sewer Lining scheduled for Late February.
Sewer point repairs started on Willow Dr. and are ongoing. Point repairs to be completed in late February and early March. Sewer lining scheduled for late April followed by service replacement.
Sewer replacement is underway on Broad St. near Orange and Moore St. Scheduled to be completed in late March.
UPCOMING WORK (in addition to the work listed above):
Point repairs on Front St. near Gordon St. (April)
MH Replacement on Crescent Drive and Short St. (April)
Sidewalk, Curb and Concrete Driveway Replacement (March-April)
SUNLAND
CONTRACT 2:
CONTRACT 3: