- See TIP 103 for preliminary site plan requirements
- You can also find examples in previous projects. Usually in the Project folder/agency-permit documents/pre-app or in A8 Outbound
Once the site plan is set you can begin the submittal process on the SDCI project portal
TIP: When filling in applicants & owners information use the LOOK UP option versus creating 'NEW'. This will help duplicating information on SDCI's portal
- If you don't know an answer ask Barbara or Leah
- It's a good idea to have Barbara or Leah double check the information
The city will take anywhere from 2 days to 2 weeks to review the pre-application. Contact SDCI if no movement has been made in the first week. Normally, once the pre-app has been approved, the project will be given a CN record number. That is what you will use in the full review permitting process.