Some of the numbers below are estimated and/or approximated.
Projects are funded by FAA, FDOT, and/or Airport.
Projects are subject to change according to FAA and FDOT funds availability and priorities.

Page last updated on 07/14/2016. 
Showing 10 items
YearDescriptionSummaryProjected CostContractorsStatus
Sort 
 
Sort 
 
Sort 
 
Sort 
 
Sort 
 
Sort 
 
YearDescriptionSummaryProjected CostContractorsStatus
2014 Master Plan Update The City Commission authorized an Airport Master Plan Update to be prepared to provide long-range airport improvement strategies that respond to the projected future demands for the Airport. Funding for this project has been received from the FAA (90%), FDOT (5%), and the Airport (5%). This study considers future airport improvements within a 20-year period.  $198,000.00 AVCON In Progress  
2014 Obstruction Clearing - Completion Removal of obstructions penetrating the Runways’ surfaces. This project will improve safety. Funding for this project has been received from FDOT (80%) and the Airport (20%). $48,450.00 Cropland Complete 
2015 Culvert Box Replacement (Seaplane Base) - Design  Design of a new culvert box by the seaplane base. The existing culvert box is deteriorating and needs to be replaced. Funding for this project has been received from FDOT (50%) and the Airport (50%). $8,806.44  Ardaman & Associates Complete 
2015 Terminal New Entrance Road Design and construction of a new entrance road connecting the intersection of Lynchburg Road/HWY 92 to the Airport’s terminal. Funding for this project has been received from FDOT (80%) and the Airport (20%). $934,192.51  Hanson - Tucker Paving Complete 
2015 Ramp Lighting Installation of new light poles at the terminal’s ramp. This project will improve safety at the ramp. $8,489.95 TECO Complete 
2015 Taxiway E - Design Design of a new taxiway connecting future Taxiway F to the approach of Runway 11. This Taxiway will improve airfield safety and make additional areas of the airport available for future development. Funding for this project has been received from the FAA (90%), FDOT (5%), and the Airport (5%).  $73,000.00 AVCON Complete 
2016 Culvert Box Replacement (Seaplane Base) - Construction  Construction of a new culvert box by the seaplane base. The existing culvert box is deteriorating and needs to be replaced. Funding for this project has been received from FDOT (50%) and the Airport (50%). $175,000.00 Ardaman & Assoc. - Tucker Paving Complete 
2016 Taxiway E - Construction Construction of a new taxiway connecting future Taxiway F to the approach of Runway 11. This Taxiway will improve airfield safety and make additional areas of the airport available for future development. Funding sources for this project will be the FAA (90%), FDOT (5%), and the Airport (5%).  $830,000.00 AVCON - Tucker Paving Construction Phase in Progress 
2016 Fuel Farm Replacement Design and construction of a new fuel farm at the airport, which will consist of one 12,000-gallon Jet A Tank, one 12,000-gallon AvGas Tank, and one 500-gallon MoGas Tank. The existing fuel farm is deteriorating and needs to be replaced. Funding for this project has been received from FDOT (80%) and the Airport (20%). $652,681.00 AVCON - American Environmental Aviation Complete 
2016 Taxiway F - Construction Construction of a new taxiway parallel to Runway 5/23. This Taxiway will improve airfield safety and make additional areas of the airport available for future development. Funding sources for this project will be the FAA (90%), FDOT (5%), and the Airport (5%). $3,500,000.00 AVCON - Tucker Paving  Construction Phase in Progress 
Showing 10 items