Bridge Closure - Work Status Update From Balfour Beatty

posted 27 Feb 2019, 07:23 by M Bain   [ updated 27 Feb 2019, 07:24 ]

Dear All 

Just a brief update: the new bridge deck is leaving the fabricators on Friday and is due to arrive on site on Monday.  It will take several days to waterproof it, ready to lowering into position on 7th March using a 150 tonne crane.

After that, we will need to bolt the sections together, before the resurfacing  of the bridge deck and approaches takes place.  This is likely to take several weeks, but I’ll send another update next week.

Best wishes

 Linzy Outtrim PhD

Stakeholder Manager | Balfour Beatty | Services | Living Places