B4214 closure now delayed until 28 November

posted 11 Oct 2018, 10:08 by M Bain   [ updated 11 Oct 2018, 10:10 ]

Following discussions with ward councillors, and local parishes, and after reviewing the available safety information, the decision has been taken by Herefordshire Council to delay the start of the safety related works to Storesbrook Bridge.  This will allow local farming businesses additional time to complete their harvest.

The road closure will now be in force from the 28th November 2018.

The condition of the bridge will be closely monitored up until the closure date and if necessary additional safety measures will be installed to keep highway users safe, this may include the earlier closure of the bridge if required.  The contractors have been asked  to provide additional resources so that the original 16 week programme is now shorter.

It is anticipated that the work will be complete by the end of February 2019.