Van's RV14a Builders Log
Paul and Victoria Rosales  with Van's RV-6A  aircraft

Project Details

SectionStart Date% CompleteHoursPage LinksCompleted Date
1-Empennage Kit November 26, 2017 100 185.0 Empennage - RV14A May 19, 2018 
2-Wings QB Kit September 7, 2018 80 7.5 Wings  
3-Fuselage QB Kit   Fuselage  
4-Engine / FWF   Engine  
5-Avionics   Avionics  
6-Misc  8.5 Misc  
Van's RV14a Total Build November 26, 2017 20 200.5   
Showing 7 items from page Project Details sorted by Section. View more »

Random Updates

  • 3 Month Project Delay I finally received the rest of my kits today and after a 3 month period of zero production I can finally get back to building. 
    Posted Sep 2, 2018, 2:40 PM by Kevin Lippert
  • Received QBK Kits Today I received the Fuselage & Wing Quick Build Kits. Also received the Finish Kit and FWF Kit.
    Posted Sep 2, 2018, 2:38 PM by Kevin Lippert
  • Slight Project Delay So I didn't realize how quickly the Empennage kit would be completed and ordered the QB Fuse / Wings a little late. They are scheduled to arrive first couple weeks ...
    Posted Jun 4, 2018, 1:25 PM by Kevin Lippert
  • Empennage Completed 56.5 Hours
    Posted May 22, 2018, 6:27 AM by Kevin Lippert
  • Elevators Completed 37.0 Hours
    Posted Mar 13, 2018, 6:18 PM by Kevin Lippert
Showing posts 1 - 5 of 16. View more »

Van's RV14a