SnowMan Team 

The University of  Vermont


Project Time Line

 November 3

  • System Deployment at Ranch Camp Site

October 29 - November2

  • Pillow and Load Cell Calibration
  • System adjustments 

October 23 - 28

  •  Four functioning stations complete

October 22

  • Project Group  Meeting
  • Single Working Prototype

August 27 - End October 

  • School Starts 
  • Build and test other stations of system
  • Create database for data logging
  • Deploy system 
July 25 - August 26
  •  Build and test Snow Pillow
  •  Complete code modification 
  •  Build main site and calibrate sensors 
  •  Field test antenna to find signal strength through snow (simulated with Zamboni ice from the Gutterson Field House Hockey Rink)
  •  Take field trip to proposed site on Mt. Mansfield