Project Updates


January 2015

posted Jan 29, 2015, 9:21 PM by Erin Fowles   [ updated Jan 29, 2015, 9:21 PM ]

Visit the media page for a video update showing the completed library, administration building, security building and water tower. Thank you to our generous donors who have made this dream come true!  The next goal is to get the library furnished and open by the end of this year!

December 2013

posted Dec 15, 2013, 7:37 PM by Erin Fowles   [ updated Dec 15, 2013, 7:37 PM ]

An early Christmas gift.... significant progress is made on the interior of the library. See the Photo Gallery for photos!

October 2013 Update

posted Nov 24, 2013, 7:32 AM by Erin Fowles

The construction on the main library building is progressing!  Roofing work is complete. Electrical piping and ceiling work are underway!

June 2013 Update

posted Jun 10, 2013, 3:26 PM by Erin Fowles

We have received an updated architectural rendering of the library and a revised bid. See the images in the Photo Gallery and the drawings on the Media page.  We are moving closer every day to making this library dream a reality for the people of Abatete!

January 2013 Update

posted Mar 10, 2013, 12:34 PM by Erin Fowles   [ updated Mar 10, 2013, 12:35 PM ]

Father Nnaso returned from a successful trip to Nigeria this January, documenting the project progress to date. On site is the administration building as well as the newly constructed water tower, which provides much needed clean water to the community.  The next phase of the project involves the transformation of the former post office building into the modern library facility!  See the latest video update on our Media page.

New Project Update Video Posted

posted May 13, 2012, 12:07 PM by Erin Fowles

Visit our Media page to view the new video describing the latest updates to our project!

Administrative Building Nearly Complete

posted Jan 24, 2012, 8:30 PM by Erin Fowles

As of Father Nnaso's departure in mid-January, construction on the Administration building is nearly complete. Roofing, ceilings, windows, outer doors, window protectors, and plastering of the building are all complete. Electrical work was 85% complete as of his departure. Thank you, Father Nnaso, for your oversight and management during this trip and thank you to ALL whose contributions are making this dream a reality for the people of Abatete! Pictures are available in the Photo Gallery.

GROUND BREAKING FOR ADMINISTRATIVE BUILDING!

posted Oct 18, 2011, 7:18 PM by Mark Serpe

Check out the pix in the Photo Gallery from the SOWL site in Abatete...We are underway with our building at last!  (Notice that we are making our own blocks right on the work site to save money!)

Our website has a new look!

posted Oct 12, 2011, 9:00 PM by Erin Fowles   [ updated Oct 12, 2011, 9:01 PM ]

We have incorporated our new logo into an updated website. We've "gone Google", and hope that this new host will make it easier for all of our committee members to keep the website updated with project news!

1-9 of 9