Welcome

 
The Somerset Berkley Regional High School Building Committee was formed to oversee the funding and construction of the new Regional High School. The purpose of this site is to keep the public informed of current activities of the committee.
 

 
 
Next Committee Meeting
Monday, December 12, 6:30pm
Somerset Berkley Regional High School
Library

Phases of Construction
July 2, 2012 - August 21, 2015
 
Phase I (July 2, 2012 - August 21, 2013)
  • Construction of new building (ongoing)
  • Construction of new tennis courts     (July '12 - Nov. '12)
  • Construction of new track and field  (December '12 - Aug. '13)
  • Installation of new water line connection to County Street, construction of temporary access and bus circulation road (July '12 - Aug. '12)
  • Construction of new south parking lot and roadway (July '13 - Aug. '13)
Phase II (August 2013 - August 2014)
  • Construction of new building
  • Construction of North parking lot
  • Construction of new baseball and softball fields
  • Construction of phased roadway in front of the new school 
Phase III (August 2014 - August 2015)
  • Demolition of existing building
  • Construction of new east parking lot
  • Construction of new roadway to County Street
  • Construction of new soccer fields
  • Construction of boulevard in front of new school building 

 
 