Project status updates, schedule and team effectiveness pages are linked below:

To do for project completion:
  • Prototype Design Description - complete, see Budget
  • How it Works - in progress, see User Manual
    • Warning and Safety Precautions - complete
    • Outer mold construction - complete
    • Inner mold construction - complete
    • Extractor construction - complete
    • Diffuser construction - complete
    • Filter housing construction - complete
    • Filling filter material - complete
    • Growing biolayer - complete
    • Suggested Maintenance and Schedule Instructions - Dave - by Saturday 12pm
    • Edit all parts - Abby - by Monday 9am
    • Formatting - Abby - by Monday 9am
  • Final Design Updates - needs written from Thursday presentation - Pete and Mike - by Monday 9am
  • How it is Made and How Much it Would Cost
    • How it is manufactured/assembled - instructions on drawings - Bill and Pete - by Monday 9am
    • Complete drawing package - Bill and Pete - by Monday 9am
      • Inner mold sub assembly description (tolerances and DFMA) - Mike and Pete - by Monday 9am
      • Outer mold sub assembly description (tolerances and DFMA) - Dave and Bill - by Monday 9am
      • Extractor sub assembly description (tolerances and DFMA) - Abby and Chris - by Monday 9am
    • Parts List - complete, see Parts List
    • Estimated Production Cost - complete, see Production Cost