Build that Hangar!

A chronicle of the construction of the MAC Hangar. Click on any picture to see a larger version.

The bare location (late August, 2012)

Excavation begins! (09.04.2012)

Soil underneath looks good! (09.06.2012)

Grading is underway. (09.06.2012)

The north wall footing, nearest to the runway (09.14.2012)

The crew hard at the east wall footing (09.14.2012)

The pour of the footing has started (09.15.2012)

The east wall footing is complete (09.15.2012)

Looking east (09.15.2012)

Aerial shot, foundation complete- Thanks Larry! (09.25.2012)

North side, looking east (09.26.2012)

West side footing wall (09.26.2012)

The steel has arrived and is being assembled! (10.03.2012)

It looks like a building! (10.09.2012)

North side, looking west (10.09.2012)

North side, looking east (10.09.2012)

West wall interior insulation (10.16.2012)

West wall siding (10.16.2012)

The roof has started, looking west (10.18.2012)

Almost half the roof is up, looking east (10.18.2012)

Insulation is down, piping for in floor heat is next (10.23.2012)

Stacks of insulation in southeast bay (10.23.2012)

Roof is complete, north side view (10.23.2012)

Another angle, southwest bay in foreground (10.23.2012)

In floor heating loops underway (10.24.2012)

Loops are complete, floor pour on the 26th (10.24.2012)

The division between the two east bays (10.24.2012)

The floor is poured (10.26.2012)

Looks pretty smooth (10.26.2012)

Pumping the concrete (10.26.2012)

Floor is curing. Looks good (10.29.2012)

Installing the dividing walls. Insulation will go in the gaps

between the rafters as well (10.30.2012)

For more pictures of the project click here.

Introducing the site of the most expensive toilet in

Westmorland County! (10.30.2012)