Welcome to the Project S2-2012  - Constraining Observations into Seismic Hazard

Coordinated by Laura Peruzza (OGS - Istituto Nazionale di Oceanografia e di Geofisica Sperimentale)
July 2012 - June 2013

Project at a Glance:

The project is the 3rd S2 Project funded in the frame of DPC-INGV Agreements. It concerns the mid-long term Seismic Hazard Assessment in Italy, focussing in betterment that can be reached in one-year project on two priority areas. 

Project Objectives

The project aims at developing a post-processing chain of seismic hazard assessment (SHA) able to:
  • combine the expected shakings at bedrock with site-specific information gathered at the regional scale
  • convert different kinds of observations (instrumental and not) into proxies of expected shakings and viceversa
  • validate the hazard maps with observations, in order to detect areas of potential underestimation of the forecasted shakings
  • compare and rank different hazard models, according to shared and well-established validation rules, in order to select the best “local” model
  • increase the knowledge about how-to-handle seismic hazard estimate in two peculiar cases, one due to site conditions (liquefactions), and the other to special plants (natural gas storages).

DELIVERABLES AVAILABLE
download them from the "Deliverables" page

30 Sept 2013GAME OVER
8 Jan 2014: The game continues on S2-2014
17 Jan 2014: GAME STOPPED
03 Feb 2014: Precisazioni
3 Apr 2014: Ripresa

1 May 2014:
Nuovo Progetto S2-2014

TO-DO List

TitleAssigned ToStatusPriorityDue DateExecution
Final scientific report Project manager 3.) Closed 4.) Critical October 15, 2013 >90% 
Finale scientific report for RUs all Research Units 3.) Closed 4.) Critical September 30, 2013 >90% 
Organization of final meeting Project manager/Task Responsibles 3.) Closed 4.) Critical September 24, 2013 >90% 
Showing 3 items from page Tasks sorted by Due Date, Priority, Status. View more »

See the Updates

  • Precisazioni A seguito di alcuni articoli apparsi sulla stampa nazionale riguardo alle attività ed alla gestione dei progetti sismologici, il Coordinatore del programma ed i tre Direttori hanno voluto fare alcune precisazioni riguardo al contenuto degli articoli citati. Il testo qui allegato è consultabile anche nella sezione "Project Documents"
    Posted Feb 3, 2014, 9:33 AM by Laura Peruzza
  • S2 continues Con la riconferma dei Direttori, la trasmissione dei commenti sulla prima annualità, e la stipula della Convenzione All. C per il 2014 riparte la progettazione DPC-INGV per i progetti sismologici.Vai alla pagina S2-2014 per ulteriori informazioni
    Posted Jan 12, 2014, 1:40 PM by Laura Peruzza
Showing posts 1 - 2 of 14. View more »

Recent Files

  • Precisazioni_notizie.pdf   22k - Feb 3, 2014, 9:34 AM by Laura Peruzza (v1)
  • S2_finalreportRT7_dec13.pdf   4318k - Jan 13, 2014, 11:56 PM by Laura Peruzza (v1)
  • Stralci verbali CP per CdPs S e V.pdf   184k - Jan 11, 2014, 8:15 AM by Laura Peruzza (v1)