2010 Maintenance & Remodel Project

The FOSL Board of  Directors has voted to fund a needed maintenance project for the book sale building and surrounding area.  This project will be completed by the end of summer, 2010. With the exception of the roofing, all labor is volunteer.

Phase I:
Lay gravel for an expanded  parking area north of the building.      COMPLETED   May, 2010

Phase II:
Construct a stage in the field east of the FOSL building. This will be used for the Children's Summer Reading Program performers. COMPLETED  June, 2010

Phase III:
Reinforce the floor in the FOSL building and construct additional shelving for book display.  New carpeting will be installed at the same time.
Scheduled for week of July 11. COMPLETED July 16, 2010

Phase IV: Re-roof the FOSL building. Scheduled for July 12-13. COMPLETED July 13, 2010


                                                         
 
 