Article 6.1.1 - Time of Performance

A party must perform its obligations:

(a) if a time is fixed by or determinable from the contract, at that time;

(b) if a period of time is fixed by or determinable from the contract, at any time within that period unless circumstances indicate that the other party is to choose a time;

(c) in any other case, within a reasonable time after the conclusion of the contract.

Article 6.1.2 - Performance at one Time or in Instalments

In cases under Article 6.1(b) or (c), a party must perform its obligations at one time if that performance can be rendered at one time ad the circumstances do not indicate otherwise.

Article 6.1.3 - Partial Performance

(1) The obligee may reject an offer to perform in part at the time performance is due, whether or not such offer is coupled with an assurance as to the balance of the performance, unless the obligee has no legitimate interest in so doing.

(2) Additional expenses caused to the obligee by partial performance are to be borne by the obligor without prejudice to any other remedy.

Article 6.1.4 - Order of Performance

(1) To the extent that the performances of the parties can be rendered simultaneously, the parties are bound to render them simultaneously unless the circumstances indicate otherwise.

(2) To the extent that the performance of only one party requires a period of time, that party is bound to render its performance first, unless the circumstances indicate otherwise.

Article 6.1.5 - Earlier Performance

(1) The obligee may reject an earlier performance unless it has no legitimate interest in so doing.

(2) Acceptability by a party of an earlier performance does not affect the time for the performance of its own obligations if that time has been fixed irrespective of the performance of the other party?s obligations.

(3) Additional expenses caused to the obligee by earlier performance are to be borne by the obligor, without prejudice to any other remedy.

Article 6.1.6 - Place of Performance

(1) If the place of performance is neither fixed by, nor determinable from the contract, a party is to perform:

(a) a monetary obligation, at the obligee?s place of business;

(b) any other obligation, at its own place of business.

(2) A party must bear any increase in the expenses incidental to performance which is caused by a change in its place of business subsequent to the conclusion of the contract.

Article 6.1.7 - Payment by Cheque or other Instrument

(1) Payment may be made in any form used in the ordinary course of business at the place for payment.

(2) However, an obligee who accepts, either by virtue of paragraph (1) or voluntarily, a cheque, any other order to pay or a promise to pay, is presumed to do so only on condition that it will be honoured.

Article 6.1.8 - Payment by Funds Transfer

(1) Unless the obligee has indicated a particular account, payment may be made by a transfer to any of the financial institutions in which the obligee has made it known that it has an account.

(2) In case of payment by a transfer of the obligation of the obligor is discharged when the transfer to the obligee?s financial institution becomes effective.

Article 6.1.9 - Currency of Payment

(1) If a monetary obligation is expressed in a currency other than that of the place of payment, it may be paid by the obligor in the currency of the place for payment unless

(a) the currency is freely convertible; or

(b) the parties have agreed that payment should be made only in the currency in which the monetary obligation is expressed.

(2) If it is impossible for the obligor to make payment in the currency in which the monetary obligation is expressed, the obligee may require payment in the currency of the place for payment, even in the case referred to in paragraph (1)(b).

(3) Payment in the currency of the place for payment is to be made according to the applicable rate of exchange prevailing there when payment is due.

(4) However, if the obligor has not paid at the time when payment is due, the obligee may require payment according to the applicable rate of exchange prevailing either when payment is due or at the time of actual payment.

Article 6.1.10 - Currency Not Expressed

Where a monetary obligation is not expressed in a particular currency, payment must be made in the currency of the place where payment is to be made.

Article 6.1.11 - Costs of Performance

Each party shall bear the costs of performance of its obligations.

Each party shall bear the costs of performance of its obligations.

Article 6.1.12 - Imputation of Payments

(1) An obligor owing several monetary obligations to the same obligee may specify at the time of payment the debt to which it intends the payment to be applied. However, the payment discharges first any expenses, then interest due and finally the principal.

(2) If the obligor makes no such specification, the obligee may, within a reasonable time after payment, declare to the obligor the obligation to which it imputes the payment, provided that the obligation is due and undisputed.

(3) In the absence of imputation under paragraphs (1) or (2), payment is imputed to that obligation which satisfies one of the following criteria and in the order indicated:

(a) an obligation which is due or which is the first to fall due;

(b) the obligation for which the obligee has least security;

(c) the obligation which is the most burdensome for the obligor;

(d) the obligation which has arisen first.

If none of the preceding criteria applies, payment is imputed to all the obligations proportionally.

Article 6.1.13 - Imputation of Non-Monetary Obligations

Article 6.1.14 - Application for Public Permission

Where the law of a State requires a public permission affecting the validity of the contract or its performance and neither that law nor the circumstances indicate otherwise

(a) if only one party has its place of business in that State, that party shall take the measures necessary to obtain the permission;

(b) in any other case the party whose performance requires permission shall take the necessary measures.

Article 6.1.15 - Procedure in Applying for Permission

(1) The party required to take the measures necessary to obtain the permission shall do so without undue delay and shall bear any expenses incurred.

(2) That party shall whenever appropriate give the other party notice of the grant or refusal of such permission without undue delay

Article 6.1.16 - Permission Neither Granted Nor Refused

(1) If, notwithstanding the fact that the party responsible has taken all measures required, permission is neither granted nor refused within an agreed period or, where no period has been agreed, within a reasonable time from the conclusion of the contract, either party is entitled to terminate the contract.

(2) Where the permission affects some terms only, paragraph (1) does not apply if, having regard to the circumstances, it is reasonable to uphold the remaining contract even if the permission is refused.

Article 6.1.17 - Permission Refused

(1) The refusal of a permission affecting the validity of the contract renders the contract void. If the refusal affects the validity of some terms only, only such terms are void if, having regard to the circumstances, it is reasonable to uphold the remaining contract.

(2) Where the refusal of a permission renders the performance of the contract impossible in whole or in part, the rules on non-performance apply.

Section 2 - Hardship

Article 6.2.1 - Contract to be Observed

Where the performance of a contract becomes more onerous for one of the parties, that party is nevertheless bound to perform its obligations subject to the following provisions on hardship.

Article 6.2.2 - Definition of Hardship

There is hardship where the occurrence of events fundamentally alters the equilibrium of the contract either because the cost of a party?s performance has increased or because the value of the performance a party receives has diminished, and

(a) the events occur or become known to the disadvantaged party after the conclusion of the contract;

(b) the events could not reasonably have been taken into account by the disadvantaged party at the time of the conclusion of the contract;

(c) the events are beyond the control of the disadvantaged party; and

(d) the risk of the events was not assumed by the disadvantaged party.

Article 6.2.3 - Effects of Hardship

(1) In case of hardship the disadvantaged party is entitled to request renegotiations. The request shall be made without undue delay and shall indicate the grounds on which it is based.

(2) The request for renegotiation does not itself entitle the disadvantaged party to withhold performance.

(3) Upon failure to reach agreement within a reasonable time either party may resort to the court.

(4) If the court finds hardship it may, if reasonable,

(a) terminate the contract at a date and on terms to be fixed; or

(b) adapt the contract with a view to restoring its equilibrium.

--

---------------------------------------------------------------------------------------

Preamble - Purpose of the Principles 

Chapter 1 - General Provisions

Chapter 2 - Formation

Chapter 3 - Validity 

Chapter 4 - Interpretation

Chapter 5 - Content

Chapter 6 - Performance 

Chapter 7 - Non-Performance 

***************************************************************************

Principles of International Commercial Contracts