Post date: Jun 27, 2010 8:50:42 PM
In 3020:
Week of June 21st
- complete carpet installation
Week of June 28th
- complete miscellaneous painting
- installation of blinds
- installation of first floor lighting
- refurbishment of staircase banister (to be verified)
- polish terrazzo and marble steps in lobby (to be verified)
Week of July 5th
- installation of first floor mirror
In 3014:
Week of June 21st
- continue painting
Week of June 28th
- complete painting
- polish terrazzo and marble steps in lobby (to be verified)
Week of July 5th
- installation of carpeting
Week of July 12th
- installation of blinds
- installation of first floor lighting
- installation of first floor mirror
- refurbishment of staircase banister (to be verified)