Project 1

Meeting Log:

2-16-11: Website creation, Team name choosing


2-20-11: Create GUI Components, Compute D-H Parameters and Matrices, Fixed Angle-Set Convention Mistakes
2-20-11: Code is now on http://code.google.com/p/roomba-project1/

2-27-11: Finalize code, Finish Documentation, Testing




Team Member Task Allocation
Showing 7 items
TitleAssigned ToStatusPriorityDue Date% Complete
Sort 
 
Sort 
 
Sort 
 
Sort 
 
Sort 
 
Sort 
 
TitleAssigned ToStatusPriorityDue Date% Complete
Create Website Everyone 3.) Closed 3.) High  100% 
Choose Team Name Everyone 3.) Closed 1.) Low  100% 
Create SVN Everyone 3.) Closed 3.) High  100% 
GUI components Anthony and Kourtney 3.) Closed 3.) High  100% 
Handout 1 corrections Matt 3.) Closed 2.) Medium  100% 
Matrix calculations Matt and Guillermo 1.) Active 3.) High  100% 
Project #1 report Guillermo 1.) Active 2.) Medium  100% 
Showing 7 items
ą
p1.PNG
(22k)
Matt Bartel,
Feb 27, 2011, 8:07 PM
Comments