$1.6 Million Alternative Fuel Heating Plant (aka Wood Chip Facility) Scope of Work

WOOD CHIP FACILITY

SCOPE OF WORK

Project Description

Estimated Cost*


Wood Chip System Inclusive            


$360,000

General Conditions

$100,00

Building Costs (30’wx50’l @ +/- $200/sf

$300,00

Excavating and Site Costs (replace paving, site work around building and site grading as required)

    $100,000

Mechanical Costs (includes connection to existing services heating and ventilation in the new building, pumps, electrical and minimal controls)

$150,000

Underground Piping Costs (500ft x +/- $150/lf

$75,000

Sub-Total

$1,085,000

Estimating Contingency 5%

$54,250

Sub-Total

$1,139,250

Mark Up 10%

$113,925

Bond 2%

$22, 785

Construction Total

$1,275,960

Project Contingency

$102, 077

Engineering and Permitting Fees (Architectural, Engineering, Air Modeling, Site and Permits)

$190,000

TOTAL COST

$1,568,037

*based on 2009 values without escalation rate