Here is a quick update:

  • contractors started work this morning (Monday, July 8) to locate and begin the process to relocate the potable water line that runs underneath Chandler Road
  • the normal northbound side of Chandler Road has been torn up and removed
  • traffic on the normal southbound side of Chandler Road has been coned off for ONE WAY Traffic. There are no signs yet indicating which way traffic is being asked to flow, but please remember that this ONE WAY lane is intended to help our community members that live adjacent to our Intermediate School the ability to get to and from their homes.

June 26, 2019

  • the city of Kilgore has started their Chandler Road Re-Pavement Project
  • this city project is expected to significantly affect traffic flow for Kilgore ISD schools...especially our Chandler Elementary Campus
  • KISD is working with the city of Kilgore and their road contractor to ensure our community's neighborhood and our District's school buses, student traffic, and parent pick up/drop off plans for the upcoming school year are created to best alleviate traffic congestion during this project
  • KISD will make every attempt to keep this site up to date with the latest news as it is received
  • the map below depicts how Chandler Road will soon be changed to ONE WAY traffic flow