Design and supply of ventilation bulkhead gantries with built in fans/scrubbers to remove dust from work area
Client: Judlau - NY Tunnel Rehab Project
Manufactured by: Nebraska Welding / KEE
Mounting system for temporary ventilation system under Madison Yard
Client: Dragados/Judlau – East Side Access
Manufactured by: American Commercial
28,000 CFM fan and scrubber installation for rib of 22’ diameter tunnel
Client: Dragados/Judlau – East Side Access
Manufactured by: Nebraska Welding
54” Heal tap elbow with blast door and weighted damper that opens when negative pressure exceeds pre-set value
Client: Tutor/Salida – Caldicott Tunnel Project
Manufactured by: Nebraska Welding
Custom engineered drop deck flat car with engineered for purpose scissor lifts that carry vent sections in low and lift into place for installation in tunnel
Client: McNally/Kiewit WRTC
Bolts Into Tunnel Rib, 32,000 CFM Fan and Scrubber System, 1000 KVA Roadheader Transformer also mounted on deck
Client: Dragados/Judlau – East Side Access
Manufactured by: American Commercial
Ducting system design for installation with limited clearance in Madison Yard
Client: Dragados/Judlau – East Side Access
Design of ventilation system, and utility support brackets for shaft and tunnel
Client: OHL – Staten Island
Bulkhead and Scavenger system provides adequate ventilation for station rebuild operations
Client: Judlau – 63rd and Lexington Station
Ventline clamshell assemblies for 54” hardline ducting on a new Robbins EPB Machine
Client: Barnard/Impregilo/Healy
Manufacturer: Nebraska Welding, LTD
Design of tunnel temporary ventilation system
Client: Judlau
Transported and relocated with strut gantry, 32,000 CFM Fan and Scrubber System, 1000 KVA Roadheader Transformer also mounted on deck
Client: Dragados/Judlau – East Side Access
Manufactured by: American Commercial
Design of 1060 HP tunnel ventilation system for TBM and Drill/Blast project
Client: Kiewit/Shea
Design of shaft and tunnel ventilation system for TBM tunnel on Hartford CSO project
Client: Kenny/Obayashi
Design of multiple shaft, tunnel, and cavern ventilation systems for final stages of East Side Access project
Client: Tutor Perini
Client: Kiewit – Harlem River Tunnel Project
Manufactured by: SMJ