Cedar High School

Concerns

  • Shared chemistry lab is antiquated and not meeting current needs

  • Age of the chemistry lab is causing safety concerns

  • Classrooms are small and crowded

The Project

  • Remodel the science wing

  • Increase the size of the classrooms

  • Remodel science labs for combined classroom and lab use

  • Estimated project sq ft

The total estimated cost of the Cedar High School Project is $5.57 Million, which is approximately 8% of the Bond Funding

Estimates include the cost of construction and soft costs such as architectural, engineering, furniture, equipment, etc. As with any estimate or projection, the actual cost of the project may vary.

The Cedar High School Project is expected to begin in the Spring of 2022

Actual start dates of the projects may vary from expectations due to economic and other factors.

Project Progress

Contract Status - Awarded to Hughes General Contractors

Guaranteed Maximum Price - $3,711,184

Estimated Construction Start Date - Spring 2022

Construction Started - April 11, 2022

Estimated Construction End Date - December 2022

Actual Construction End Date - TBD

Final Cost - TBD