Cedar High School
Concerns
Shared chemistry lab is antiquated and not meeting current needs
Age of the chemistry lab is causing safety concerns
Classrooms are small and crowded
The Project
Remodel the science wing
Increase the size of the classrooms
Remodel science labs for combined classroom and lab use
Estimated project sq ft
The total estimated cost of the Cedar High School Project is $5.57 Million, which is approximately 8% of the Bond Funding
Estimates include the cost of construction and soft costs such as architectural, engineering, furniture, equipment, etc. As with any estimate or projection, the actual cost of the project may vary.
The Cedar High School Project is expected to begin in the Spring of 2022
Actual start dates of the projects may vary from expectations due to economic and other factors.
Project Progress
Contract Status - Awarded to Hughes General Contractors
Guaranteed Maximum Price - $3,711,184
Estimated Construction Start Date - Spring 2022
Construction Started - April 11, 2022
Estimated Construction End Date - December 2022
Actual Construction End Date - TBD
Final Cost - TBD